Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks
Exam 1: Introduction: Why Project Management103 Questions
Exam 2: The Organizational Context: Strategy, Structure, and Culture103 Questions
Exam 3: Project Selection and Portfolio Management99 Questions
Exam 4: Leadership and the Project Manager101 Questions
Exam 5: Scope Management103 Questions
Exam 6: Project Team Building, Conflict, and Negotiation102 Questions
Exam 7: Risk Management98 Questions
Exam 8: Cost Estimation and Budgeting102 Questions
Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path105 Questions
Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks96 Questions
Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain101 Questions
Exam 12: Resource Management99 Questions
Exam 13: Project Evaluation and Control104 Questions
Exam 14: Project Closeout and Termination101 Questions
Select questions type
Quite often the marginal gains in employee productivity decrease dramatically with the increased use of overtime.
(True/False)
4.9/5
(30)
If an activity's cost is plotted against its duration on axes with zeros at the origin:
(Multiple Choice)
4.9/5
(35)
Dummy activities are used in AOA networks to indicate the existence of precedent relationships between activities and their event nodes.
(True/False)
4.8/5
(35)
A project manager ascertained that five different resources are needed to complete a project that has been estimated to last 37 days. Just to be on the safe side, the project manager told the client that the project would definitely be delivered in 40 days and 40 nights and arranged to rent the resources for that period of time. The project manager goes to the local rental center at the start of day 1 of the project, signs a 40-day lease agreement for all five resources, and brings them to the site to begin the project. Analyze the Gantt chart and resource list (activity durations are in parenthesis) and determine how much money is being wasted with this rental plan. If each resource could be rented for just the time it takes to complete each activity, what would the charge to the project be?




(Essay)
4.7/5
(31)
The heir to the throne was due 60 days from now and the first-time father had a serious construction project on his hands converting his man cave into a nursery. The seven activities, their normal and expedited times (in days) and costs appear in the table. Just to be on the safe side, he decided to bring the project in at 53 days in case the delivery was a week early. Tell him what the least expensive 53-day project is; which activities should be reduced in duration, by how many days, and at the total cost, so he can roll up the sleeves on his "World's Greatest Dad" sweatshirt, and get to work.


(Essay)
4.9/5
(32)
-Use the Gantt chart and activity list to determine which resource has the greatest continual use. 


(Multiple Choice)
4.8/5
(32)
What are four criticisms and caveats to bear in mind as you develop a project activity network?
(Essay)
4.7/5
(40)
Crashing costs for a project are governed by the function:
50t2 + 100t
where t represents the number of days crashed (see graph). The project manager wants to crash the project, and is willing to pay up to $1,000 per day saved. How many days can be saved before the per-day cost is too high? 

(Essay)
4.9/5
(34)
A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the lowest total cost for completing this project in 33 weeks?


(Essay)
4.9/5
(39)
What is the minimum cost completion time for this project if the activities have normal and crash costs as indicated and there is a $1,000 fixed cost for each day on site plus a $500 penalty for each activity that is crashed? The crash costs represent the cost of a fully expedited activity. For example, reducing activity Y from 13 days to 12 days costs an extra $100 on top of the $500 expediting cost for a total cost of $2,600. Reducing Y from 13 days to 10 days costs an extra $300 on top of the $500 expediting cost, for a total activity cost of $2,800.


(Essay)
5.0/5
(34)
A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $4,000 per week for every week the project exceeds 37 weeks. What is the lowest total cost for completing this project? 

(Multiple Choice)
4.9/5
(34)
Most activity estimations using PERT methods lead to overly optimistic activity duration estimates.
(True/False)
4.8/5
(39)
Networks are adaptable and useful for all scheduling challenges that an organization faces.
(True/False)
4.9/5
(38)
Mick has a project consisting of eight activities (listed in the table with durations and precedence requirements) to complete. He assigned his intern Guinness to sketch a network diagram in AOA and Guinness produced the sketch shown below. Discuss any issues with the apprentice's diagram.



(Essay)
4.8/5
(34)
Showing 41 - 60 of 96
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)