Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks
Exam 1: Introduction: Why Project Management103 Questions
Exam 2: The Organizational Context: Strategy, Structure, and Culture103 Questions
Exam 3: Project Selection and Portfolio Management99 Questions
Exam 4: Leadership and the Project Manager101 Questions
Exam 5: Scope Management103 Questions
Exam 6: Project Team Building, Conflict, and Negotiation102 Questions
Exam 7: Risk Management98 Questions
Exam 8: Cost Estimation and Budgeting102 Questions
Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path105 Questions
Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks96 Questions
Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain101 Questions
Exam 12: Resource Management99 Questions
Exam 13: Project Evaluation and Control104 Questions
Exam 14: Project Closeout and Termination101 Questions
Select questions type
What are the three principal methods for accelerating a project and under what circumstances might these methods yield little gain?
(Essay)
4.9/5
(41)
Use the information in the table to create a baseline Gantt chart for the project where activity lengths are given in days.


(Essay)
4.8/5
(37)
-Use the Gantt chart and the activity list to determine which resource is used the most. 


(Multiple Choice)
4.9/5
(32)
A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $6,000 per week for every week the project extends beyond 25 weeks. What is the lowest total cost duration for completing this project? 

(Multiple Choice)
4.9/5
(33)
-Use the Gantt chart and activity list to determine which resource has the greatest continual use. 


(Multiple Choice)
4.9/5
(34)
Sketch a network and use it as an example as you discuss the four different logical relationships between activities.
(Essay)
4.9/5
(30)
-What is the late finish for activity D in the network shown in the diagram?

(Multiple Choice)
4.8/5
(31)
A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the lowest total cost for completing this project in 33 weeks? 

(Multiple Choice)
4.9/5
(29)
-Use the Gantt chart and the activity list to determine which resource is needed earliest in this project. 


(Multiple Choice)
4.9/5
(30)
It costs $75 per day for each day that a construction crew is on site. The project manager determines that most activities can be crashed and has listed the crashing costs next to the minimum time for each activity. Use this information to determine the lowest cost for this project. All times given are in days. 

(Multiple Choice)
4.8/5
(33)
Brook's Law states that the typical crashing decision to add more resources to an activity only delays the activity further.
(True/False)
4.9/5
(38)
Activities A and B have a finish to finish relationship and early start and finish times as shown. What is the result of incorporating a 4-day lag between activities C and B? 

(Multiple Choice)
4.9/5
(34)
Showing 61 - 80 of 96
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)