Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

  -What is the duration of the project shown in the network? -What is the duration of the project shown in the network?

(Multiple Choice)
4.9/5
(30)

A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the total cost for completing this project in 40 days? A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the total cost for completing this project in 40 days?

(Multiple Choice)
4.7/5
(37)

Use the information in the table (all times are in days) to determine the lowest cost minimum completion time if the base cost for each activity finished in normal time is $1,000. Use the information in the table (all times are in days) to determine the lowest cost minimum completion time if the base cost for each activity finished in normal time is $1,000.

(Multiple Choice)
4.7/5
(32)

  -Use the Gantt chart and activity list to determine when resource 3 is free.  -Use the Gantt chart and activity list to determine when resource 3 is free.   -Use the Gantt chart and activity list to determine when resource 3 is free.

(Multiple Choice)
4.9/5
(43)

A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $250 per week for every week the project extends beyond 32 weeks. What is the duration of the least expensive project possible? A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $250 per week for every week the project extends beyond 32 weeks. What is the duration of the least expensive project possible?

(Multiple Choice)
4.9/5
(33)

The process of accelerating a project is referred to as:

(Multiple Choice)
4.8/5
(49)

For large projects, network diagrams are more useful if they are completely detailed.

(True/False)
4.8/5
(33)

What is the cost to finish this project (all activity durations are in weeks and costs in US dollars) as quickly as possible? What is the cost to finish this project (all activity durations are in weeks and costs in US dollars) as quickly as possible?

(Essay)
4.8/5
(37)

  -Use the Gantt chart and the activity list to determine which resource is free for use in another project before the others.  -Use the Gantt chart and the activity list to determine which resource is free for use in another project before the others.   -Use the Gantt chart and the activity list to determine which resource is free for use in another project before the others.

(Multiple Choice)
4.9/5
(38)

Use the information in the table (all times are in days) to determine the lowest extra cost for an 18-day project if the base cost for each activity finished in normal time is $1,000. Use the information in the table (all times are in days) to determine the lowest extra cost for an 18-day project if the base cost for each activity finished in normal time is $1,000.

(Multiple Choice)
4.9/5
(28)

The BEST approach to network representation of a large and hugely complex project is to:

(Multiple Choice)
4.8/5
(44)

A finish to start lag delay is usually shown:

(Multiple Choice)
4.8/5
(33)

A complex project that is managed using a top-down, bottom-up approach to network diagrams means that:

(Multiple Choice)
4.8/5
(36)

The heir to the throne was due 56 days from now and the first-time father had a serious construction project on his hands converting his man cave into a nursery. The seven activities, their normal and expedited times (in days) and costs appear in the table. What is the minimum cost to ensure that this project is completed in 56 days? Which activities should be reduced and by how many days? The heir to the throne was due 56 days from now and the first-time father had a serious construction project on his hands converting his man cave into a nursery. The seven activities, their normal and expedited times (in days) and costs appear in the table. What is the minimum cost to ensure that this project is completed in 56 days? Which activities should be reduced and by how many days?

(Essay)
4.9/5
(25)

Given the cost information in the table, what is the cheapest activity to crash on a per week basis? Given the cost information in the table, what is the cheapest activity to crash on a per week basis?

(Multiple Choice)
4.9/5
(26)

  -Use the Gantt chart and activity list to determine which resource is used the least.  -Use the Gantt chart and activity list to determine which resource is used the least.   -Use the Gantt chart and activity list to determine which resource is used the least.

(Multiple Choice)
4.9/5
(31)

One reason for crashing a project is:

(Multiple Choice)
4.9/5
(45)

  -Use the Gantt chart and activity list to determine which resource is released from this project for use in another project the earliest.  -Use the Gantt chart and activity list to determine which resource is released from this project for use in another project the earliest.   -Use the Gantt chart and activity list to determine which resource is released from this project for use in another project the earliest.

(Multiple Choice)
4.9/5
(37)

In an actual project, one means of crashing critical path activities would be to perform at a lower level of quality.

(True/False)
4.9/5
(45)

The critical path may not contain a dummy activity.

(True/False)
4.9/5
(35)
Showing 21 - 40 of 96
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)