Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path
Exam 1: Introduction: Why Project Management103 Questions
Exam 2: The Organizational Context: Strategy, Structure, and Culture103 Questions
Exam 3: Project Selection and Portfolio Management99 Questions
Exam 4: Leadership and the Project Manager101 Questions
Exam 5: Scope Management103 Questions
Exam 6: Project Team Building, Conflict, and Negotiation102 Questions
Exam 7: Risk Management98 Questions
Exam 8: Cost Estimation and Budgeting102 Questions
Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path105 Questions
Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks96 Questions
Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain101 Questions
Exam 12: Resource Management99 Questions
Exam 13: Project Evaluation and Control104 Questions
Exam 14: Project Closeout and Termination101 Questions
Select questions type
Use the information in the table to determine the early start time for Activity B. 

(Multiple Choice)
4.9/5
(34)
The amount of time an activity may be delayed from its early start without delaying the finish of the project is the:
(Multiple Choice)
4.8/5
(38)
There's an old saying, "The job is not finished until the paperwork is done." From an activity network standpoint, this does not necessarily mean that the paperwork can't begin until the last non-paperwork activity is completed. It might be possible to work on some paperwork as early activities are completed. In order to depict this in an activity network:
(Multiple Choice)
4.8/5
(45)
Draw a network of any size that has at least one of each of the following features: merge activity, burst activity, hammock activity, ladder activity, critical path, serial activities, concurrent activities, and float. Mark these features on your network.
(Essay)
4.9/5
(40)
A sequence of activities defined by the project network logic is a(n):
(Multiple Choice)
4.8/5
(37)
What is the early finish time for Activity F given the activity times and precedence requirements shown in the table? 

(Multiple Choice)
4.7/5
(31)
What does a network diagram illustrate and why are they important in project management?
(Essay)
4.8/5
(47)
Use the information in the table to determine the slack time for Activity B. 

(Multiple Choice)
4.9/5
(48)
Ray's shipment of materials hit every red light and traffic jam on the way to the site. Upon arrival, half of the material was judged defective, necessitating a trip back to the supplier, and then the same arduous journey back to the site once the new materials were loaded. Traffic was a little better on the second round but the flat tire and subsequent repair caused as much if not more delay than the first trip. In the final analysis:
(Multiple Choice)
4.8/5
(35)
A gentleman farmer maniacally works on academic projects to raise funds for his true passion, farming. He has identified seven tasks and developed three time estimates (all in days) of the next big project on the farm, replacing the fence at the comedy pasture. Tasks, precedence requirements, and time estimates are shown in the table. What is the probability that the project takes more than 34 days? 

(Multiple Choice)
4.9/5
(30)
An activity has an optimistic time estimate of 17 days, a most likely estimate of 22 days, and a pessimistic estimate of 32 days. What is the expected duration of the activity?
(Multiple Choice)
4.9/5
(33)
An activity has an expected duration and an expected cost. Another name for an activity is a(n):
(Multiple Choice)
4.8/5
(38)
Which technique would accelerate the completion of a project?
(Multiple Choice)
4.8/5
(32)
Activity float is the difference between the late finish and early finish for the activity in question.
(True/False)
4.8/5
(28)
What is the float start time for Activity C given the activity times and precedence requirements shown in the table? 

(Multiple Choice)
5.0/5
(33)
Use the information in the table to determine the early finish time for Activity D. 

(Multiple Choice)
4.9/5
(31)
Showing 41 - 60 of 105