Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Use the information in the table to sketch the network and compute early and late start times. Use the information in the table to sketch the network and compute early and late start times.

(Essay)
4.9/5
(35)

  -Which of these statements about this network is BEST? -Which of these statements about this network is BEST?

(Multiple Choice)
4.9/5
(38)

A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides to represent a few activities by a hammock activity. Which is a legitimate hammock activity for this project? A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides to represent a few activities by a hammock activity. Which is a legitimate hammock activity for this project?

(Multiple Choice)
4.8/5
(43)

What is the late start time for Activity B given the activity times and precedence requirements shown in the table? What is the late start time for Activity B given the activity times and precedence requirements shown in the table?

(Multiple Choice)
4.7/5
(42)

The overall effect of laddering activities is to:

(Multiple Choice)
4.7/5
(37)

At a burst point in a backward pass, the largest succeeding late start becomes the late finish for that node.

(True/False)
4.7/5
(39)

Construct a network using the information in the table and identify the critical path. Construct a network using the information in the table and identify the critical path.

(Essay)
4.7/5
(39)

Compute early and late start and finish times for the network shown. Compute early and late start and finish times for the network shown.

(Essay)
4.7/5
(38)

An activity has a pessimistic time that is four times as long as its most likely time and six times as long as its optimistic time. If the activity variance is 12, what is the expected time?

(Multiple Choice)
4.8/5
(34)

A gentleman farmer maniacally works on academic projects to raise funds for his true passion, farming. He has identified seven tasks and developed three time estimates (all in days) of the next big project on the farm, replacing the fence at the comedy pasture. Tasks, precedence requirements, and time estimates are shown in the table. What is the late finish for the Plant Posts activity? A gentleman farmer maniacally works on academic projects to raise funds for his true passion, farming. He has identified seven tasks and developed three time estimates (all in days) of the next big project on the farm, replacing the fence at the comedy pasture. Tasks, precedence requirements, and time estimates are shown in the table. What is the late finish for the Plant Posts activity?

(Multiple Choice)
4.9/5
(31)

The BEST candidate activities for shortening the overall project are:

(Multiple Choice)
4.9/5
(40)

  -Use the network diagram and activity lengths in the nodes to determine the slack time for activity D. -Use the network diagram and activity lengths in the nodes to determine the slack time for activity D.

(Multiple Choice)
4.8/5
(34)

In general, the better candidates for shortening are:

(Multiple Choice)
4.8/5
(43)

A gentleman farmer maniacally works on academic projects to raise funds for his true passion, farming. He has identified seven tasks and developed three time estimates (all in days) of the next big project on the farm, replacing the fence at the comedy pasture. Tasks, precedence requirements, and time estimates are shown in the table. What is the probability that the project is completed in 31 days? A gentleman farmer maniacally works on academic projects to raise funds for his true passion, farming. He has identified seven tasks and developed three time estimates (all in days) of the next big project on the farm, replacing the fence at the comedy pasture. Tasks, precedence requirements, and time estimates are shown in the table. What is the probability that the project is completed in 31 days?

(Multiple Choice)
4.8/5
(26)

Project Test Bank is composed of activities we will refer to as A, B, C, and D for convenience (and lack of creativity). Durations and precedence requirements are shown in the table. Each of these activities can be conveniently laddered into two sub-activities of equal duration. The first half of each activity serves as the predecessor to its second half and the first half of the original following activity. What is the expected completion time of the laddered project? Project Test Bank is composed of activities we will refer to as A, B, C, and D for convenience (and lack of creativity). Durations and precedence requirements are shown in the table. Each of these activities can be conveniently laddered into two sub-activities of equal duration. The first half of each activity serves as the predecessor to its second half and the first half of the original following activity. What is the expected completion time of the laddered project?

(Multiple Choice)
4.9/5
(30)

What is laddering and what advantages can be gained from its use in project management?

(Essay)
4.8/5
(40)

What are three methods of duration estimation for project activities and what are the advantages and disadvantages of each method?

(Essay)
4.9/5
(34)

The term ordered activity means:

(Multiple Choice)
4.8/5
(36)

What is the slack time for Activity B given the activity times and precedence requirements shown in the table? What is the slack time for Activity B given the activity times and precedence requirements shown in the table?

(Multiple Choice)
4.8/5
(25)

Float is always measured in exactly the same way as slack.

(True/False)
4.8/5
(36)
Showing 61 - 80 of 105
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)