Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path
Exam 1: Introduction: Why Project Management103 Questions
Exam 2: The Organizational Context: Strategy, Structure, and Culture103 Questions
Exam 3: Project Selection and Portfolio Management99 Questions
Exam 4: Leadership and the Project Manager101 Questions
Exam 5: Scope Management103 Questions
Exam 6: Project Team Building, Conflict, and Negotiation102 Questions
Exam 7: Risk Management98 Questions
Exam 8: Cost Estimation and Budgeting102 Questions
Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path105 Questions
Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks96 Questions
Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain101 Questions
Exam 12: Resource Management99 Questions
Exam 13: Project Evaluation and Control104 Questions
Exam 14: Project Closeout and Termination101 Questions
Select questions type
Use the information in the table to sketch the network and compute early and late start times.


(Essay)
4.9/5
(35)
A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides to represent a few activities by a hammock activity. Which is a legitimate hammock activity for this project? 

(Multiple Choice)
4.8/5
(43)
What is the late start time for Activity B given the activity times and precedence requirements shown in the table? 

(Multiple Choice)
4.7/5
(42)
At a burst point in a backward pass, the largest succeeding late start becomes the late finish for that node.
(True/False)
4.7/5
(39)
Construct a network using the information in the table and identify the critical path.


(Essay)
4.7/5
(39)
An activity has a pessimistic time that is four times as long as its most likely time and six times as long as its optimistic time. If the activity variance is 12, what is the expected time?
(Multiple Choice)
4.8/5
(34)
A gentleman farmer maniacally works on academic projects to raise funds for his true passion, farming. He has identified seven tasks and developed three time estimates (all in days) of the next big project on the farm, replacing the fence at the comedy pasture. Tasks, precedence requirements, and time estimates are shown in the table. What is the late finish for the Plant Posts activity? 

(Multiple Choice)
4.9/5
(31)
The BEST candidate activities for shortening the overall project are:
(Multiple Choice)
4.9/5
(40)
-Use the network diagram and activity lengths in the nodes to determine the slack time for activity D.

(Multiple Choice)
4.8/5
(34)
A gentleman farmer maniacally works on academic projects to raise funds for his true passion, farming. He has identified seven tasks and developed three time estimates (all in days) of the next big project on the farm, replacing the fence at the comedy pasture. Tasks, precedence requirements, and time estimates are shown in the table. What is the probability that the project is completed in 31 days? 

(Multiple Choice)
4.8/5
(26)
Project Test Bank is composed of activities we will refer to as A, B, C, and D for convenience (and lack of creativity). Durations and precedence requirements are shown in the table. Each of these activities can be conveniently laddered into two sub-activities of equal duration. The first half of each activity serves as the predecessor to its second half and the first half of the original following activity. What is the expected completion time of the laddered project? 

(Multiple Choice)
4.9/5
(30)
What is laddering and what advantages can be gained from its use in project management?
(Essay)
4.8/5
(40)
What are three methods of duration estimation for project activities and what are the advantages and disadvantages of each method?
(Essay)
4.9/5
(34)
What is the slack time for Activity B given the activity times and precedence requirements shown in the table? 

(Multiple Choice)
4.8/5
(25)
Showing 61 - 80 of 105
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)