Exam 11: Aggregate Planning and Master Scheduling
Exam 1: Introduction to Operations Management78 Questions
Exam 2: Competitiveness, Strategy, and Productivity75 Questions
Exam 3: Forecasting144 Questions
Exam 4: Product and Service Design100 Questions
Exam 5: Strategic Capacity Planning for Products and Services210 Questions
Exam 6: Process Selection and Facility Layout137 Questions
Exam 7: Work Design and Measurement200 Questions
Exam 8: Location Planning and Analysis65 Questions
Exam 9: Management of Quality101 Questions
Exam 10: Quality Control117 Questions
Exam 11: Aggregate Planning and Master Scheduling80 Questions
Exam 12: Inventory Management134 Questions
Exam 13: MRP and ERP85 Questions
Exam 14: Jit and Lean Operations126 Questions
Exam 15: Supply Chain Management91 Questions
Exam 16: Scheduling102 Questions
Exam 17: Project Management118 Questions
Exam 18: Management of Waiting Lines68 Questions
Exam 19: Linear Programming98 Questions
Select questions type
Which of the following would not be a strategy associated with adjusting aggregate capacity to meet expected demand?
(Multiple Choice)
4.9/5
(25)
A firm has 43 units of a certain product on hand. Forecasts for the first two planning periods are 20 units each. A production quantity of 80 units is planned to be available in period 3. Customer orders are 22 for period 1 and 17 for period 2. What quantity is available for commitment to new customers in either of the first two periods?
(Multiple Choice)
4.9/5
(35)
Aggregate planning is used to establish general levels of employment, output, and inventories over an intermediate range of time.
(True/False)
4.8/5
(39)
Aggregate planners are concerned with the quality and quantity of expected demand.
(True/False)
4.9/5
(35)
One thing that makes aggregate planning in services easier than aggregate planning in manufacturing is
(Multiple Choice)
4.7/5
(35)
Information for firm ABC
What is the expected inventory at the end of April 2008?

(Multiple Choice)
4.9/5
(28)
Which one of the following would not be considered a decision option for purposes of aggregate planning?
(Multiple Choice)
4.8/5
(38)
A firm has 56 units of product X on hand. Forecasts of demand are for 20 units per week. An MPS quantity of 100 units is planned to arrive in period 3. Customer orders are 24 for period 1, 18 for period 2, and 15 for period 3.
What quantity is available for commitment to new customers prior to the receipt of the MPS quantity in week 3?
(Multiple Choice)
4.9/5
(37)
Organizations facing seasonal changes in demand are prevented from using aggregate planning techniques.
(True/False)
4.9/5
(30)
Information for firm ABC
What was the inventory at the end of March 2008?

(Multiple Choice)
4.7/5
(26)
The direct result of disaggregating the aggregate plan is the
(Multiple Choice)
4.9/5
(38)
That portion of projected inventory which enables marketing to make realistic commitments about delivery dates for new orders is
(Multiple Choice)
4.8/5
(33)
Which of the following are typically in play in a circumstance in which yield management is worthwhile?
(I)Perishable capacity(II)Ample finished goods storage(III)Demand variability(IV)Low holding costs
(Multiple Choice)
4.7/5
(30)
In practice, the more commonly used techniques for aggregate planning are
(Multiple Choice)
4.9/5
(39)
In using the chase strategy, variations in demand could be met by
(Multiple Choice)
4.8/5
(36)
The assignment of work to specific machines and people are examples of aggregate planning.
(True/False)