Exam 17: Project Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

At which point does crashing of a project cease?

Free
(Multiple Choice)
4.8/5
(32)
Correct Answer:
Verified

C

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated expected (mean)time for activity D? What is the estimated expected (mean)time for activity D?

Free
(Multiple Choice)
5.0/5
(31)
Correct Answer:
Verified

E

The latest starting time for an activity is equal to the latest finish time minus the activity time.

Free
(True/False)
4.8/5
(39)
Correct Answer:
Verified

True

If two consecutive activities have shared slack, this means that each of them can use only half of the slack without delaying completion of the project.

(True/False)
4.8/5
(37)

In the execution phase of a project's life cycle, activities are guided by decisions that were made in the __________ phase.

(Multiple Choice)
4.9/5
(37)

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated standard deviation in the time for activity Z? What is the estimated standard deviation in the time for activity Z?

(Multiple Choice)
4.9/5
(28)

Which of the following is not one of the six key decisions in project management? (I)Selecting the project team(II)Deciding on the project manager's title(III)Managing and controlling project resources(IV)Deciding which projects to implement(V)Selecting the project manager

(Multiple Choice)
4.8/5
(39)

Which of the following are limitations of PERT and CPM?(I)Time estimates may include a fudge factor.(II)Important activities may be overlooked.(III)It is an after-the-fact analysis.

(Multiple Choice)
4.9/5
(38)

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated expected (mean)time for activity Y? What is the estimated expected (mean)time for activity Y?

(Multiple Choice)
4.8/5
(33)

In order to determine the probability of timely project completion, it is sometimes necessary to take into account paths other than the critical path.

(True/False)
4.9/5
(42)

A project is represented by the following diagram: A project is represented by the following diagram:   The critical path for the network shown is: The critical path for the network shown is:

(Multiple Choice)
4.8/5
(31)

The path in a network with the average length of time to completion is called the critical path.

(True/False)
4.8/5
(34)

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the probability that this project will be completed within 130 days? What is the probability that this project will be completed within 130 days?

(Multiple Choice)
4.8/5
(28)

Concerning PERT and CPM

(Multiple Choice)
4.8/5
(32)

If the expected length of a path is more than 2.5 standard deviations less than a desired project completion time, the path will not be a factor in assessing the probability of finishing the project on time.

(True/False)
4.9/5
(38)

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated expected (mean)time for activity E? What is the estimated expected (mean)time for activity E?

(Multiple Choice)
4.9/5
(40)

All of the following are areas of knowledge that a project manager should possess, except

(Multiple Choice)
4.9/5
(28)

The total cost of crashing any one activity should never exceed 20 percent of the total cost of the original project.

(True/False)
4.7/5
(29)

Activity 7-8 is directly preceded by two activities-activity 5-7 and activity 6-7. Activity 5-7 has an expected time of five and an ES time of six. Activity 6-7 has an expected time of seven and an ES time of seven. Activity 7-8 has an expected time of 10. The ES for activity 7-8 is

(Multiple Choice)
4.7/5
(29)

Gantt charts are most closely associated with

(Multiple Choice)
4.9/5
(27)
Showing 1 - 20 of 118
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)