Exam 17: Project Management
Exam 1: Introduction to Operations Management78 Questions
Exam 2: Competitiveness, Strategy, and Productivity75 Questions
Exam 3: Forecasting144 Questions
Exam 4: Product and Service Design100 Questions
Exam 5: Strategic Capacity Planning for Products and Services210 Questions
Exam 6: Process Selection and Facility Layout137 Questions
Exam 7: Work Design and Measurement200 Questions
Exam 8: Location Planning and Analysis65 Questions
Exam 9: Management of Quality101 Questions
Exam 10: Quality Control117 Questions
Exam 11: Aggregate Planning and Master Scheduling80 Questions
Exam 12: Inventory Management134 Questions
Exam 13: MRP and ERP85 Questions
Exam 14: Jit and Lean Operations126 Questions
Exam 15: Supply Chain Management91 Questions
Exam 16: Scheduling102 Questions
Exam 17: Project Management118 Questions
Exam 18: Management of Waiting Lines68 Questions
Exam 19: Linear Programming98 Questions
Select questions type
At which point does crashing of a project cease?
Free
(Multiple Choice)
4.8/5
(32)
Correct Answer:
C
Consider the following work breakdown structure:
What is the estimated expected (mean)time for activity D?

Free
(Multiple Choice)
5.0/5
(31)
Correct Answer:
E
The latest starting time for an activity is equal to the latest finish time minus the activity time.
Free
(True/False)
4.8/5
(39)
Correct Answer:
True
If two consecutive activities have shared slack, this means that each of them can use only half of the slack without delaying completion of the project.
(True/False)
4.8/5
(37)
In the execution phase of a project's life cycle, activities are guided by decisions that were made in the __________ phase.
(Multiple Choice)
4.9/5
(37)
Consider the following work breakdown structure:
What is the estimated standard deviation in the time for activity Z?

(Multiple Choice)
4.9/5
(28)
Which of the following is not one of the six key decisions in project management?
(I)Selecting the project team(II)Deciding on the project manager's title(III)Managing and controlling project resources(IV)Deciding which projects to implement(V)Selecting the project manager
(Multiple Choice)
4.8/5
(39)
Which of the following are limitations of PERT and CPM?(I)Time estimates may include a fudge factor.(II)Important activities may be overlooked.(III)It is an after-the-fact analysis.
(Multiple Choice)
4.9/5
(38)
Consider the following work breakdown structure:
What is the estimated expected (mean)time for activity Y?

(Multiple Choice)
4.8/5
(33)
In order to determine the probability of timely project completion, it is sometimes necessary to take into account paths other than the critical path.
(True/False)
4.9/5
(42)
A project is represented by the following diagram:
The critical path for the network shown is:

(Multiple Choice)
4.8/5
(31)
The path in a network with the average length of time to completion is called the critical path.
(True/False)
4.8/5
(34)
Consider the following work breakdown structure:
What is the probability that this project will be completed within 130 days?

(Multiple Choice)
4.8/5
(28)
If the expected length of a path is more than 2.5 standard deviations less than a desired project completion time, the path will not be a factor in assessing the probability of finishing the project on time.
(True/False)
4.9/5
(38)
Consider the following work breakdown structure:
What is the estimated expected (mean)time for activity E?

(Multiple Choice)
4.9/5
(40)
All of the following are areas of knowledge that a project manager should possess, except
(Multiple Choice)
4.9/5
(28)
The total cost of crashing any one activity should never exceed 20 percent of the total cost of the original project.
(True/False)
4.7/5
(29)
Activity 7-8 is directly preceded by two activities-activity 5-7 and activity 6-7. Activity 5-7 has an expected time of five and an ES time of six. Activity 6-7 has an expected time of seven and an ES time of seven. Activity 7-8 has an expected time of 10. The ES for activity 7-8 is
(Multiple Choice)
4.7/5
(29)
Showing 1 - 20 of 118
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)