Exam 9: Resourcing Projects

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

What methods could a project manager use to resolve resource overloads?

(Essay)
4.8/5
(28)

  Figure 8-3 Programmers Resource Histogram -Consider the programmers resource histogram presented in Figure 8-3.How many programmers are required during the fifth week of this project?  Figure 8-3 Programmers Resource Histogram -Consider the programmers resource histogram presented in Figure 8-3.How many programmers are required during the fifth week of this project? 

(Multiple Choice)
5.0/5
(36)

When estimating resource needs,project teams should consider all the following EXCEPT:​ 

(Multiple Choice)
4.7/5
(32)

When recruiting resources to support a project,it is helpful to bring core team members and key subject matter experts on board as early as possible,to help plan the project and develop the project culture.

(True/False)
4.8/5
(40)

Crashing almost always accelerates the schedule while increasing project risk,whereas fast tracking almost always accelerates the schedule while increasing project cost.

(True/False)
4.9/5
(29)

  Figure 8-3 Programmers Resource Histogram -Critical Chain method was developed to address several problems that are common in organizations that use traditional project scheduling.Which of the following describes a common problem addressed by the critical chain method?  Figure 8-3 Programmers Resource Histogram -Critical Chain method was developed to address several problems that are common in organizations that use traditional project scheduling.Which of the following describes a common problem addressed by the critical chain method? 

(Multiple Choice)
4.8/5
(37)

  Figure 8-1 RACI Chart -Consider the RACI chart presented in Figure 8-1.What responsibility should the contract officer assume with respect to the statement of work?​  Figure 8-1 RACI Chart -Consider the RACI chart presented in Figure 8-1.What responsibility should the contract officer assume with respect to the statement of work?​ 

(Multiple Choice)
4.7/5
(29)

  Figure 8-4 Project Crashing Information -Consider the project crashing information presented in Figure 8-4.What is the incremental cost to achieve a one-day reduction in the duration of this project in the most cost efficient manner?​  Figure 8-4 Project Crashing Information -Consider the project crashing information presented in Figure 8-4.What is the incremental cost to achieve a one-day reduction in the duration of this project in the most cost efficient manner?​ 

(Multiple Choice)
4.8/5
(42)

Which of these is NOT an issue to be considered when selecting team members? 

(Multiple Choice)
4.9/5
(37)

  Figure 8-1 RACI Chart -Consider the RACI chart presented in Figure 8-1.Who is accountable for the data requirements?​  Figure 8-1 RACI Chart -Consider the RACI chart presented in Figure 8-1.Who is accountable for the data requirements?​ 

(Multiple Choice)
4.9/5
(40)

One approach to identifying which activities contribute to work overload for a particular resource is to compare the resource histogram to the Gantt chart schedule,using the same timescale.

(True/False)
4.8/5
(46)

Project managers find many advantages in having diverse teams,as considering diverse perspectives in making decisions can help avoid major risks that a single perspective would not uncover.

(True/False)
4.8/5
(40)

An example of fast tracking a project schedule would be to overlap the design and production phases for a design-to-production project,where the conventional approach would be to move on to construction only after completing the design phase.

(True/False)
4.8/5
(36)

What should a project manager's considerations be when resourcing projects?

(Essay)
4.8/5
(35)

  Figure 8-2 Software Programmer Loading Chart -Consider the software programmer loading chart presented in Figure 8-2.Which of the following statements most accurately describes the loading of the software programmer?​  Figure 8-2 Software Programmer Loading Chart -Consider the software programmer loading chart presented in Figure 8-2.Which of the following statements most accurately describes the loading of the software programmer?​ 

(Multiple Choice)
4.7/5
(38)

  Figure 8-3 Programmers Resource Histogram -Consider the programmers resource histogram presented in Figure 8-3.If only six programmers are available to support this project,which of the following conclusions is valid?  Figure 8-3 Programmers Resource Histogram -Consider the programmers resource histogram presented in Figure 8-3.If only six programmers are available to support this project,which of the following conclusions is valid? 

(Multiple Choice)
5.0/5
(43)

A common tool project teams use is a responsibility assignment matrix (RAM).Typically,this chart will depict:​ 

(Multiple Choice)
4.9/5
(36)

Estimate Activity Resources focuses exclusively upon the identification of the number of human resources required to perform each scheduled activity.

(True/False)
4.8/5
(45)

  Figure 8-4 Project Crashing Information -Consider the project crashing information presented in Figure 8-4.What is the cost to complete this project in the normal time?​  Figure 8-4 Project Crashing Information -Consider the project crashing information presented in Figure 8-4.What is the cost to complete this project in the normal time?​ 

(Multiple Choice)
4.9/5
(35)

Crashing is a project schedule compression technique that expedites a project by executing activities at the same time that ordinarily would be done one after the other.

(True/False)
4.8/5
(34)
Showing 21 - 40 of 45
close modal