Exam 13: Project Evaluation and Control
Exam 1: Introduction: Why Project Management105 Questions
Exam 2: The Organizational Context: Strategy, Structure, and Culture105 Questions
Exam 3: Project Selection and Portfolio Management103 Questions
Exam 4: Leadership and the Project Manager112 Questions
Exam 5: Scope Management111 Questions
Exam 6: Project Team Building, Conflict, and Negotiation102 Questions
Exam 7: Risk Management102 Questions
Exam 8: Cost Estimation and Budgeting105 Questions
Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path105 Questions
Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks96 Questions
Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain105 Questions
Exam 12: Resource Management98 Questions
Exam 13: Project Evaluation and Control107 Questions
Exam 14: Project Closeout and Termination101 Questions
Select questions type
Use the earned value table for Project Makeready to determine the earned value at week 49. Activity 7 14 21 28 35 42 49 Plan \%/1 Complete Install fixtures 325 250 575 100\% Refinish floors 550 85 635 100\% Replace doors 350 275 625 100\% Complete tiling 1,200 565 1,765 80\% Install back door 875 225 1,100 70\% Landscaping 200 350 550 25\% Monthly Plan 325 800 435 1,475 1,440 425 350 5,250 Monthly Act 550 550 550 1,100 1,650 550 1,100
Free
(Multiple Choice)
4.8/5
(35)
Correct Answer:
C
It is possible to measure both positive and negative deviations from the schedule baseline with the tracking Gantt chart.
Free
(True/False)
4.8/5
(26)
Correct Answer:
True
The earned value of a project is the cumulative total costs incurred in accomplishing the various work packages.
Free
(True/False)
4.8/5
(33)
Correct Answer:
False
What is a tracking Gantt chart and what are the benefits and drawbacks of its use?
(Essay)
4.8/5
(38)
If significant deviations from the project plan are detected,corrective action is taken and then:
(Multiple Choice)
4.9/5
(37)
A project manager can calculate the projected budget to completion by using the:
(Multiple Choice)
4.8/5
(30)
Duration (weeks)
5 10 15 20 25 \% Conceptual desiern 10 6 100\% Craphics desigrl 12 6 4 100\% Copyright 4 5 6 100\% Barmples 4 2 70\% Toolirg 6 9 4 50\% Production 2 6 14 20\% Total 10 18 22 26 24 Currulative 10 28 50 76 100
-At the end of week 25,this project has cost $79,000 and has an earned value as indicated in the table.Use the data to calculate the cost performance index for the project.All amounts are in thousands of dollars.
(Multiple Choice)
4.9/5
(29)
Briefly describe the important differences between Earned Value Management and Earned Schedule.Why is Earned Schedule gaining acceptance in project management circles?
(Essay)
4.8/5
(32)
Positive variance on an S-curve is not always a sign of significant project progress.
(True/False)
4.9/5
(38)
Briefly describe any seven critical success factors for project success contained in the Project Implementation Profile.
(Essay)
4.8/5
(31)
What is the significance of the 0/100 rule and the 50/50 rule and why would each be used?
(Essay)
4.8/5
(44)
Use the data to calculate the schedule performance index for the project for the end of week 20.The earned value as of the end of week 20 is indicated in the table.All amounts are in thousands of dollars. Duration (weeks)
5 10 15 20 25 \% Conceptual desiern 10 6 100\% Craphics desigrl 12 6 4 100\% Copyright 4 5 6 60\% Barmples 4 2 100\% Toolirg 6 9 4 50\% Production 2 6 14 20\% Total 10 18 22 26 24 Currulative 10 28 50 76 100
(Multiple Choice)
4.8/5
(40)
A recurring problem with establishing accurate or meaningful EVM results has to do with:
(Multiple Choice)
4.9/5
(37)
In earned value management,schedule variance is defined as:
(Multiple Choice)
4.8/5
(46)
What are any four benefits to using milestones as a form of project control? What advantage do they hold over pure S-curve analysis?
(Essay)
4.8/5
(37)
Sketch the project control cycle and discuss the activities that take place in each step.
(Essay)
4.8/5
(35)
A project manager needs the work breakdown structure and a time-phased project budget to establish the project baseline.
(True/False)
4.9/5
(35)