Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain
Exam 1: Introduction: Why Project Management105 Questions
Exam 2: The Organizational Context: Strategy, Structure, and Culture105 Questions
Exam 3: Project Selection and Portfolio Management103 Questions
Exam 4: Leadership and the Project Manager112 Questions
Exam 5: Scope Management111 Questions
Exam 6: Project Team Building, Conflict, and Negotiation102 Questions
Exam 7: Risk Management102 Questions
Exam 8: Cost Estimation and Budgeting105 Questions
Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path105 Questions
Exam 10: Project Scheduling: Lagging, Crashing, and Activity Networks96 Questions
Exam 11: Advanced Topics in Planning and Scheduling: Agile and Critical Chain105 Questions
Exam 12: Resource Management98 Questions
Exam 13: Project Evaluation and Control107 Questions
Exam 14: Project Closeout and Termination101 Questions
Select questions type
A key element of extreme programming is:
Free
(Multiple Choice)
4.7/5
(28)
Correct Answer:
C
A project is represented by the activity durations (estimated at 90% likelihood of completion)and precedence requirements shown in the table.What is the length of the feeder buffer if this project is managed using critical chain methodology? Activity Predecessor Length Activity Predecessor Length - 20 16 A 20 8 A 10 , 8
Free
(Multiple Choice)
4.9/5
(38)
Correct Answer:
C
The Central Limit Theorem says that if a number of probability distributions are summed:
Free
(Multiple Choice)
4.8/5
(33)
Correct Answer:
B
The term capacity constraint buffer refers to a safety margin separating different tasks scheduled to use the same resource.
(True/False)
4.9/5
(24)
A project consists of four activities with information as shown in the table.What is the overall variance of the project? Standard Activity Predecessor Length Deviation A - 10 2 B A 12 1 C B 16 2 D C 14 3
(Multiple Choice)
4.7/5
(36)
Effective agile project management recognizes that a project's goals should not adapted or reshaped during the development cycle.
(True/False)
4.7/5
(27)
Subcontractor deliveries are difficult to schedule with the critical chain project methodology because:
(Multiple Choice)
4.9/5
(28)
A project is represented by the activity durations (estimated at 90% likelihood of completion)and precedence requirements shown in the table.What is the length of the feeder buffer for path NQT if this project is managed using critical chain methodology? Activity Predecessor Length Activity Predecessor Length - 8 -- 12 - 8 14 12 , 7 10 , 11
(Multiple Choice)
4.9/5
(31)
A project consists of four consecutive tasks that have average duration and worst-case duration estimates (in days)as shown in the table.Use Newbold's model to determine the aggregated buffer of one standard deviation for this project. Activity Average Worst-Case 12 20 20 25 14 24 18 26
(Multiple Choice)
4.9/5
(34)
The buffers supplied to non-critical paths in critical chain project management are called:
(Multiple Choice)
4.9/5
(36)
Use these activity durations (that have been estimated at 90%)and precedence requirements to create two project schedules-a traditional schedule based on early start times and a critical chain schedule with buffers.
Activity Time Predecessor 8 15 19 12 3 16 12 16 7 16 , 12 8 ,
(Essay)
4.8/5
(36)
A project is represented by the activity durations (in days,estimated at 90% likelihood of completion)and precedence requirements shown in the table.What is the length of the project buffer if this project is managed using critical chain methodology? Use the rule of thumb approach. Activity Predecessor Lengenth Activity Predecessor Length A -- 18 , 13 B - 16 9 22 , 15 14
(Multiple Choice)
4.8/5
(34)
A project consists of four consecutive tasks that have average duration and worst-case duration estimates (in days)as shown in the table.Use Goldratt's model to determine the aggregated buffer for this project. Activity Average Worst-Case 10 20 15 25 20 30 25 35
(Multiple Choice)
4.8/5
(26)
Traditional,highly structured approaches to planning and managing projects are recognized as being less effective for ________ than Agile Project Management.
(Multiple Choice)
4.8/5
(37)
Goldratt's solution to the variables involved in project scheduling involves the aggregation,or collectivizing,of all project risk in the form of uncertain duration estimates and completion times.Provide practical examples of how this aggregation works to the benefit of the overall project.
(Essay)
4.8/5
(31)
Use the project information in the table to resolve resource conflicts,identify the critical chain and critical path,and create feeder buffers.The project buffer follows: Activity Predecessor Length Resource Activity Predecessor Length Resource A - 11 P D C 13 P B A 7 M E - 12 8 14
(Multiple Choice)
4.9/5
(38)
A project consists of six consecutive tasks that have average duration and worst-case duration estimates (in days)as shown in the table.Use Newbold's method to determine the aggregated two sigma buffer for this project. Activity Average Worst-Case A 14 21 20 28 16 22 8 15 9 18 11 18
(Multiple Choice)
4.8/5
(34)
Showing 1 - 20 of 105
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)