Exam 11: Aggregate Planning and Master Scheduling

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Demand can be altered in aggregate planning by promotion and producing additional product using overtime.

(True/False)
4.9/5
(27)

Aggregate planning is capacity planning for:

(Multiple Choice)
4.8/5
(39)

Subcontracting 'in' would apply to periods in which our organization has excess capacity.

(True/False)
4.7/5
(29)

That portion of projected inventory which enables marketing to make realistic commitments about delivery dates for new orders is:

(Multiple Choice)
4.8/5
(40)

Capacity can be modified in aggregate planning by promotion and producing additional product using overtime.

(True/False)
4.7/5
(37)

Ultimately the overriding factor in choosing a strategy in aggregate planning is overall cost.

(True/False)
4.7/5
(37)

In order to use the "level capacity strategy," variations in demand are met by:

(Multiple Choice)
4.7/5
(39)

The more __________ demand is, the more the aggregate plan will tend to reflect the ____________ strategy.

(Multiple Choice)
4.8/5
(36)

The main disadvantage(s) of informal techniques used for aggregate planning is(are):

(Multiple Choice)
4.8/5
(28)

A time fence in the master schedule is used to prevent unauthorized people from making changes to the schedule.

(True/False)
4.9/5
(33)

What are total overtime costs?

(Short Answer)
4.8/5
(32)

Simulation to produce an aggregate plan:

(Multiple Choice)
4.9/5
(42)

Which of the following is not an input to the aggregate planning process?

(Multiple Choice)
4.9/5
(41)

Which one of the following would not be considered a decision option for purposes of aggregate planning?

(Multiple Choice)
5.0/5
(42)

Inventory information for firm ABC: Inventory information for firm ABC:   What was the inventory at the end of March, 1999? What was the inventory at the end of March, 1999?

(Multiple Choice)
5.0/5
(41)

Which of the following best describes aggregate planning?

(Multiple Choice)
4.8/5
(42)

One option for altering the availability of manufacturing capacity is:

(Multiple Choice)
4.9/5
(38)

Aggregate planners attempt to balance:

(Multiple Choice)
4.8/5
(38)

In practice, the more commonly used techniques for aggregate planning are:

(Multiple Choice)
4.9/5
(42)

Which of the following differs between aggregate planning in services and aggregate planning in manufacturing?

(Multiple Choice)
4.8/5
(42)