Exam 11: Aggregate Planning and Master Scheduling
Exam 1: Introduction to Operations Management70 Questions
Exam 2: Competitiveness, Strategy, and Productivity73 Questions
Exam 3: Forecasting164 Questions
Exam 4: Product and Service Design77 Questions
Exam 5: Strategic Capacity Planning for Products and Services103 Questions
Exam 6: Process Selection and Facility Layout151 Questions
Exam 7: Work Design and Measurement151 Questions
Exam 8: Location Planning and Analysis80 Questions
Exam 9: Management of Quality102 Questions
Exam 10: Quality Control141 Questions
Exam 11: Aggregate Planning and Master Scheduling81 Questions
Exam 12: MRP and ERP89 Questions
Exam 13: Inventory Management162 Questions
Exam 14: Jit and Lean Operations88 Questions
Exam 15: Supply Chain Management89 Questions
Exam 16: Scheduling134 Questions
Exam 17: Project Management137 Questions
Exam 18: Management of Waiting Lines81 Questions
Exam 19: Linear Programming105 Questions
Exam 20: Extension 4: Reliability10 Questions
Exam 21: Extension 5: Decision Theory126 Questions
Exam 22: Extension 7: Learning Curves68 Questions
Exam 23: Extension 8: The Transportation Model20 Questions
Exam 24: Extension 10: Acceptance Sampling65 Questions
Exam 25: Extension 14: Maintenance38 Questions
Select questions type
Moving from the aggregate plan to a master production schedule requires:
(Multiple Choice)
4.7/5
(30)
The direct result of disaggregating the aggregate plan is the:
(Multiple Choice)
4.8/5
(35)
The use of tables and charts in aggregate planning usually enables planners to arrive at an optimal plan.
(True/False)
4.7/5
(33)
A level capacity strategy is also known as a chase demand strategy.
(True/False)
4.9/5
(38)
Which of the following is not a basic option for altering the availability of capacity in a service environment?
(Multiple Choice)
4.9/5
(34)
The master schedule indicates the quantity and timing for delivery of a product, but not the dates production will need to start.
(True/False)
4.9/5
(34)
A master production schedule quantity of 300 units will arrive in week 6.Weekly demand over weeks 3 through 10 is forecasted at 50 units.At present, orders have been booked in various quantities in weeks 1, 2, 3 and 4.What is the available to promise for week 6?
(Multiple Choice)
4.7/5
(40)
Inventory information for firm ABC:
What is the expected inventory at the end of April, 1999?

(Multiple Choice)
4.8/5
(37)
Aggregate planners are concerned with the quality and quantity of expected demand.
(True/False)
4.8/5
(40)
Which one of the following is not a basic option for altering demand?
(Multiple Choice)
4.9/5
(39)
What is the projected on hand inventory at the end of period 2?
(Multiple Choice)
4.7/5
(42)
Organizations facing seasonal changes in demand are prevented from using aggregate planning techniques.
(True/False)
4.9/5
(35)
The assignment of work to specific machines and people are examples of aggregate planning.
(True/False)
4.9/5
(27)