Exam 11: Aggregate Planning and Master Scheduling
Exam 1: Introduction to Operations Management70 Questions
Exam 2: Competitiveness, Strategy, and Productivity73 Questions
Exam 3: Forecasting164 Questions
Exam 4: Product and Service Design77 Questions
Exam 5: Strategic Capacity Planning for Products and Services103 Questions
Exam 6: Process Selection and Facility Layout151 Questions
Exam 7: Work Design and Measurement151 Questions
Exam 8: Location Planning and Analysis80 Questions
Exam 9: Management of Quality102 Questions
Exam 10: Quality Control141 Questions
Exam 11: Aggregate Planning and Master Scheduling81 Questions
Exam 12: MRP and ERP89 Questions
Exam 13: Inventory Management162 Questions
Exam 14: Jit and Lean Operations88 Questions
Exam 15: Supply Chain Management89 Questions
Exam 16: Scheduling134 Questions
Exam 17: Project Management137 Questions
Exam 18: Management of Waiting Lines81 Questions
Exam 19: Linear Programming105 Questions
Exam 20: Extension 4: Reliability10 Questions
Exam 21: Extension 5: Decision Theory126 Questions
Exam 22: Extension 7: Learning Curves68 Questions
Exam 23: Extension 8: The Transportation Model20 Questions
Exam 24: Extension 10: Acceptance Sampling65 Questions
Exam 25: Extension 14: Maintenance38 Questions
Select questions type
What quantity is available for commitment to new customers in either of the first two periods?
(Multiple Choice)
4.8/5
(40)
Aggregate planning is intermediate-range capacity planning that typically covers a time horizon of one to three months.
(True/False)
4.9/5
(43)
In the master production schedule, production is planned for the next period whenever the available-to-promise quantity becomes negative.
(True/False)
4.9/5
(38)
Which of the following would not be a strategy associated with adjusting aggregate capacity to meet expected demand?
(Multiple Choice)
4.9/5
(37)
The goal of aggregate planning is to achieve a production plan that attempts to balance the organization's resources and meet expected demand.
(True/False)
4.8/5
(39)
Which of the following steps is necessary to ensure that a master schedule is valid?
(Multiple Choice)
4.8/5
(36)
Given the projected demands for the next six months, prepare an aggregate plan that uses inventory, regular time and overtime, and backorders.The plan must wind up with no units in ending inventory in Period 6.Regular time capacity is 150 units per month.Overtime capacity is 20 units per month.Overtime cost is $30 per unit, backorder cost is $20 per unit, inventory holding cost is $5 per unit, regular time cost of $20 per unit, and beginning inventory is zero.
(Essay)
4.9/5
(38)
Master schedulers are employed primarily by service organizations.
(True/False)
4.8/5
(37)
Aggregate planning is used to establish general levels of employment, output, and inventories over an intermediate-range of time.
(True/False)
4.7/5
(39)
Aggregate planning requires which of the following information?
(Multiple Choice)
4.8/5
(40)
Use either the transportation method or linear programming to develop an optimum aggregate plan, given the following data:
(Essay)
4.8/5
(25)
After the first period of the planning horizon, available-to-promise is computed only for those periods in which there is an MPS quantity.
(True/False)
4.9/5
(34)
What is the projected on-hand inventory at the end of period 2?
(Multiple Choice)
4.7/5
(40)
Accommodating peak demands and effectively using labor resources during periods of low demand would be the goal of aggregate planners in ....
(Multiple Choice)
4.8/5
(38)
Showing 61 - 80 of 81