Exam 7: Scheduling Activities
Exam 1: Introduction to Project Management49 Questions
Exam 2: Project Selection and Prioritization52 Questions
Exam 3: Organizational Capability: Structure,Culture and Roles50 Questions
Exam 4: Chartering Projects39 Questions
Exam 5: Stakeholder Analysis and Communication Planning46 Questions
Exam 6: Defining Scope and Constructing Work Breakdown Structures WBS44 Questions
Exam 7: Scheduling Activities56 Questions
Exam 8: Resourcing Projects45 Questions
Exam 9: Budgeting Projects46 Questions
Exam 10: Project Risk Planning45 Questions
Exam 11: Project Quality Planning and Project Kick-Off45 Questions
Exam 12: Project Supply Chain Management45 Questions
Exam 13: Leading and Managing Project Teams46 Questions
Exam 14: Determining Project Progress and Results44 Questions
Exam 15: Finishing the Project30 Questions
Select questions type
Figure 7-4 Lab Experiment Project
-Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,which activity can be delayed one day without impacting the expected project completion date?

(Multiple Choice)
4.9/5
(31)
Figure 7-6 Network Scheduling Data
-Consider the network scheduling data presented in Figure 7-6.How many days of slack are associated with activity F?

(Multiple Choice)
4.9/5
(46)
In order for activities to be useful as schedule building blocks,they should have tangible output that can be verified.
(True/False)
4.9/5
(31)
Figure 7-4 Lab Experiment Project
-Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,identify the critical path(s)for this project?

(Multiple Choice)
4.8/5
(35)
The sequencing of activities is often based upon dependencies between the activities.The dependencies that should guide activity sequencing can be either:
(Multiple Choice)
4.9/5
(35)
The first process in developing a project schedule is to identify all the resources available to work on the project.
(True/False)
4.7/5
(40)
Even small delays on "near-critical" activities can change the critical path of a project.
(True/False)
4.9/5
(42)
Which of the following responses identifies a common type of logical dependency used to sequence project activities?
(Multiple Choice)
4.8/5
(33)
Creating a realistic schedule is often an iterative process because several factors can limit how fast a project can be completed.All of the following factors can limit how fast a project can be scheduled and completed EXCEPT:
(Multiple Choice)
4.8/5
(37)
The length of time to perform an activity is often dependent upon who will do that work.
(True/False)
4.9/5
(30)
The amount of time a schedule activity can be delayed without delaying the early start date of any successor is known as:
(Multiple Choice)
4.9/5
(39)
Milestones are important points in a project schedule that can serve as check points for project managers and sponsors.All of the following reasons might justify the decision to establish a milestone EXCEPT:
(Multiple Choice)
4.7/5
(40)
An activity that logically comes before a dependent activity in a schedule is called a ___:
(Multiple Choice)
5.0/5
(41)
Figure 7-5 Duration Estimates
-Consider the activity duration estimates presented in Figure 7-5.Based on the information provided and adopting the PERT conventions to calculate expected activity durations,what is the expected duration of Activity D - "Package Item"?

(Multiple Choice)
4.7/5
(33)
A mandatory dependency in a relationship that is contractually required or inherent in the nature of the work.
(True/False)
4.9/5
(33)
Describe "slack" and how you can use slack to your advantage in managing a project.
(Essay)
4.8/5
(36)
If a project manager delays the start of an activity on the critical path,then the expected completion date of the project will occur at a later date than originally planned.
(True/False)
4.8/5
(39)
Except in rare circumstances,project teams should not attempt to decompose work packages into project activities because work packages provide sufficient detail to develop a project schedule.
(True/False)
4.7/5
(42)
The critical path is the sequence of activities that represent the shortest path through the project,which determines the shortest possible duration of the project.
(True/False)
4.8/5
(44)
Figure 7-4 Lab Experiment Project
-Consider the Lab Experiment Project depicted in Figure 7-4.Based on the information provided,what is the expected duration of this project?

(Multiple Choice)
4.8/5
(32)