Exam 19: CD - Pertcpm Models for Project Management
Exam 1: Introduction28 Questions
Exam 2: Linear Programming: Basic Concepts83 Questions
Exam 3: Linear Programming: Formulation and Applications58 Questions
Exam 4: The Art of Modeling With Spreadsheets31 Questions
Exam 5: What-If Analysis for Linear Programming63 Questions
Exam 6: Network Optimization Problems48 Questions
Exam 7: Using Binary Integer Programming to Deal With Yes-Or-No Decisions26 Questions
Exam 8: Nonlinear Programming53 Questions
Exam 9: Decision Analysis77 Questions
Exam 10: Cd Supplement - Decision Analysis26 Questions
Exam 11: Forecasting76 Questions
Exam 12: Queueing Models75 Questions
Exam 13: CD Supplement - Additional Queueing Models8 Questions
Exam 14: Computer Simulation: Basic Concepts45 Questions
Exam 15: CD Supplement - the Inverse Transformation Method for Generating Random Observations2 Questions
Exam 16: Computer Simulation With Crystal Ball53 Questions
Exam 17: CD - Solution Concepts for Linear Programming45 Questions
Exam 18: CD - Transportation and Assignment Problems48 Questions
Exam 19: CD - Pertcpm Models for Project Management93 Questions
Exam 20: CD - Goal Programming21 Questions
Exam 21: CD - Inventory Management With Known Demand64 Questions
Exam 22: CD - Inventory Management With Uncertain Demand43 Questions
Select questions type
Activity C has an early start time of 8,an early finish time of 12,a latest start time of 13,and a latest finish time of 17.Its slack is:
(Multiple Choice)
4.9/5
(30)
Once a project is underway,the project manager is responsible for effectively managing:
(Multiple Choice)
4.9/5
(36)
Activity C in a project network has an optimistic time estimate of five days,a most likely time estimate of seven days,and a pessimistic time estimate of nine days.Its expected duration is approximately:
(Multiple Choice)
4.8/5
(40)
The standard deviation of the critical path is equal to the sum of the standard deviations of all the activities on the critical path.
(True/False)
4.9/5
(26)
In order to determine the probability of timely project completion,it is sometimes necessary to take into account paths other than the critical path.
(True/False)
4.9/5
(37)
If the variance of an activity duration is equal to 1 then all the durations are the same.
(True/False)
4.7/5
(34)
Only activities on the critical path are initial candidates for crashing.
(True/False)
4.9/5
(27)
The CPM method provides an excellent procedure for evaluating time-cost tradeoffs.
(True/False)
4.8/5
(33)
AON project networks have which of the following advantages over AOA networks?
(Multiple Choice)
4.9/5
(39)
Figure
(time in days)
-What is the estimated slack time for activity A?

(Multiple Choice)
4.7/5
(39)
Figure
(time in days)
-What is the estimated standard deviation in the time for activity Z?

(Multiple Choice)
4.7/5
(37)
The path in a project network with the average duration is the critical path.
(True/False)
4.7/5
(39)
In an Activity-On-Node project network,the nodes are used to separate an activity from each of its immediate predecessors.
(True/False)
4.8/5
(42)
Figure
(time in days)
-What is the estimated mean time for activity E?

(Multiple Choice)
4.9/5
(41)
Project managers must often function in an environment that is beset with uncertainties.
(True/False)
4.8/5
(29)