Exam 19: CD - Pertcpm Models for Project Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Activity C has an early start time of 8,an early finish time of 12,a latest start time of 13,and a latest finish time of 17.Its slack is:

(Multiple Choice)
4.9/5
(30)

PERT/Cost:

(Multiple Choice)
4.9/5
(28)

Once a project is underway,the project manager is responsible for effectively managing:

(Multiple Choice)
4.9/5
(36)

Activity C in a project network has an optimistic time estimate of five days,a most likely time estimate of seven days,and a pessimistic time estimate of nine days.Its expected duration is approximately:

(Multiple Choice)
4.8/5
(40)

PERT/CPM can answer which of the following questions?

(Multiple Choice)
4.8/5
(29)

The standard deviation of the critical path is equal to the sum of the standard deviations of all the activities on the critical path.

(True/False)
4.9/5
(26)

In order to determine the probability of timely project completion,it is sometimes necessary to take into account paths other than the critical path.

(True/False)
4.9/5
(37)

If the variance of an activity duration is equal to 1 then all the durations are the same.

(True/False)
4.7/5
(34)

Only activities on the critical path are initial candidates for crashing.

(True/False)
4.9/5
(27)

The CPM method provides an excellent procedure for evaluating time-cost tradeoffs.

(True/False)
4.8/5
(33)

AON project networks have which of the following advantages over AOA networks?

(Multiple Choice)
4.9/5
(39)

Which of the following is not a feature of PERT/CPM?

(Multiple Choice)
4.9/5
(39)

An important assumption in PERT calculations is:

(Multiple Choice)
4.8/5
(43)

Which of the following are ways of crashing an activity?

(Multiple Choice)
4.9/5
(32)

Figure Figure   (time in days) -What is the estimated slack time for activity A? (time in days) -What is the estimated slack time for activity A?

(Multiple Choice)
4.7/5
(39)

Figure Figure   (time in days) -What is the estimated standard deviation in the time for activity Z? (time in days) -What is the estimated standard deviation in the time for activity Z?

(Multiple Choice)
4.7/5
(37)

The path in a project network with the average duration is the critical path.

(True/False)
4.7/5
(39)

In an Activity-On-Node project network,the nodes are used to separate an activity from each of its immediate predecessors.

(True/False)
4.8/5
(42)

Figure Figure   (time in days) -What is the estimated mean time for activity E? (time in days) -What is the estimated mean time for activity E?

(Multiple Choice)
4.9/5
(41)

Project managers must often function in an environment that is beset with uncertainties.

(True/False)
4.8/5
(29)
Showing 61 - 80 of 93
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)