Exam 19: CD - Pertcpm Models for Project Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Figure Figure   (time in days) -What is the probability that this project will be completed within 205 days? (time in days) -What is the probability that this project will be completed within 205 days?

(Multiple Choice)
4.9/5
(35)

When calculating the probability that a project will finish by a certain time,the approximation that is obtained is usually lower than the true probability.

(True/False)
4.9/5
(31)

In PERT,the path with the fewest activities is referred to as the critical path.

(True/False)
4.8/5
(45)

Concerning PERT and CPM:

(Multiple Choice)
4.9/5
(38)

The values assigned to the nodes in a project network are there to identify the precedence relationships.

(True/False)
4.9/5
(35)

In project network analysis,slack refers to the difference between:

(Multiple Choice)
4.8/5
(39)

If two paths are tied for the longest duration,both would be considered to be critical paths.

(True/False)
4.9/5
(30)

Figure Figure   (time in days) -What is the estimated mean time for project completion? (time in days) -What is the estimated mean time for project completion?

(Multiple Choice)
4.8/5
(36)

Figure Figure   (time in days) -What is the estimated mean time for activity E? (time in days) -What is the estimated mean time for activity E?

(Multiple Choice)
4.8/5
(34)

A normal distribution is usually used to describe the form of the probability distribution of activity durations in the PERT three-estimate approach.

(True/False)
4.8/5
(39)

Projects involve routine activities that are performed repeatedly.

(True/False)
4.9/5
(43)

A manager has decided that an activity has a pessimistic estimate of 15 days,a most-likely estimate of 6 days,and an optimistic estimate of 3 days.The expected duration of this activity is 6 days.

(True/False)
4.7/5
(34)

The latest finish of an activity is the earliest late start of any immediately preceding activity.

(True/False)
4.8/5
(38)

A Gantt chart of a project shows the scheduled start and finish times for activities.

(True/False)
4.9/5
(37)

A common assumption when using PERT/Cost is that the costs are incurred at a constant rate throughout the duration of an activity.

(True/False)
4.7/5
(42)

The length of the critical path is determined by adding the expected completion times for all the activities in the project.

(True/False)
4.8/5
(26)

Although PERT and CPM were originally developed for somewhat different types of projects,they are now nearly identical in terms of analysis and procedures.

(True/False)
4.8/5
(34)

A forward pass is the process of moving forward through the project network to determine the latest start times and latest finish times of each activity.

(True/False)
4.9/5
(40)

Figure Figure   -The duration of the critical path is: -The duration of the critical path is:

(Multiple Choice)
4.7/5
(38)

There are four activities on the critical path,and they have standard deviations of 1,2,4,and 2 days.The standard deviation of the critical path is:

(Multiple Choice)
4.9/5
(33)
Showing 41 - 60 of 93
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)