Exam 19: CD - Pertcpm Models for Project Management
Exam 1: Introduction28 Questions
Exam 2: Linear Programming: Basic Concepts83 Questions
Exam 3: Linear Programming: Formulation and Applications58 Questions
Exam 4: The Art of Modeling With Spreadsheets31 Questions
Exam 5: What-If Analysis for Linear Programming63 Questions
Exam 6: Network Optimization Problems48 Questions
Exam 7: Using Binary Integer Programming to Deal With Yes-Or-No Decisions26 Questions
Exam 8: Nonlinear Programming53 Questions
Exam 9: Decision Analysis77 Questions
Exam 10: Cd Supplement - Decision Analysis26 Questions
Exam 11: Forecasting76 Questions
Exam 12: Queueing Models75 Questions
Exam 13: CD Supplement - Additional Queueing Models8 Questions
Exam 14: Computer Simulation: Basic Concepts45 Questions
Exam 15: CD Supplement - the Inverse Transformation Method for Generating Random Observations2 Questions
Exam 16: Computer Simulation With Crystal Ball53 Questions
Exam 17: CD - Solution Concepts for Linear Programming45 Questions
Exam 18: CD - Transportation and Assignment Problems48 Questions
Exam 19: CD - Pertcpm Models for Project Management93 Questions
Exam 20: CD - Goal Programming21 Questions
Exam 21: CD - Inventory Management With Known Demand64 Questions
Exam 22: CD - Inventory Management With Uncertain Demand43 Questions
Select questions type
Figure
(time in days)
-What is the probability that this project will be completed within 205 days?

(Multiple Choice)
4.9/5
(35)
When calculating the probability that a project will finish by a certain time,the approximation that is obtained is usually lower than the true probability.
(True/False)
4.9/5
(31)
In PERT,the path with the fewest activities is referred to as the critical path.
(True/False)
4.8/5
(45)
The values assigned to the nodes in a project network are there to identify the precedence relationships.
(True/False)
4.9/5
(35)
In project network analysis,slack refers to the difference between:
(Multiple Choice)
4.8/5
(39)
If two paths are tied for the longest duration,both would be considered to be critical paths.
(True/False)
4.9/5
(30)
Figure
(time in days)
-What is the estimated mean time for project completion?

(Multiple Choice)
4.8/5
(36)
Figure
(time in days)
-What is the estimated mean time for activity E?

(Multiple Choice)
4.8/5
(34)
A normal distribution is usually used to describe the form of the probability distribution of activity durations in the PERT three-estimate approach.
(True/False)
4.8/5
(39)
Projects involve routine activities that are performed repeatedly.
(True/False)
4.9/5
(43)
A manager has decided that an activity has a pessimistic estimate of 15 days,a most-likely estimate of 6 days,and an optimistic estimate of 3 days.The expected duration of this activity is 6 days.
(True/False)
4.7/5
(34)
The latest finish of an activity is the earliest late start of any immediately preceding activity.
(True/False)
4.8/5
(38)
A Gantt chart of a project shows the scheduled start and finish times for activities.
(True/False)
4.9/5
(37)
A common assumption when using PERT/Cost is that the costs are incurred at a constant rate throughout the duration of an activity.
(True/False)
4.7/5
(42)
The length of the critical path is determined by adding the expected completion times for all the activities in the project.
(True/False)
4.8/5
(26)
Although PERT and CPM were originally developed for somewhat different types of projects,they are now nearly identical in terms of analysis and procedures.
(True/False)
4.8/5
(34)
A forward pass is the process of moving forward through the project network to determine the latest start times and latest finish times of each activity.
(True/False)
4.9/5
(40)
There are four activities on the critical path,and they have standard deviations of 1,2,4,and 2 days.The standard deviation of the critical path is:
(Multiple Choice)
4.9/5
(33)
Showing 41 - 60 of 93
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)