Exam 19: CD - Pertcpm Models for Project Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Given this information about activity H: ES = 10,EF = 15,LS = 16,and LF = 21,we can determine that the amount of slack associated with the activity is:

(Multiple Choice)
4.7/5
(35)

A project manager does not need to monitor each individual activity,just the overall project when looking at budget costs.

(True/False)
4.7/5
(28)

In a project network the critical path is the sequence of activities which has:

(Multiple Choice)
4.7/5
(42)

Figure Figure   Given this network: -The expected duration of this project is: Given this network: -The expected duration of this project is:

(Multiple Choice)
4.8/5
(37)

An activity in a project network cannot begin until all of the activities leading into that activity have been completed.

(True/False)
4.7/5
(32)

Figure Figure   -The critical path is: -The critical path is:

(Multiple Choice)
4.9/5
(38)

In crashing a project,a manager will generally focus on activities which:

(Multiple Choice)
4.8/5
(36)

The latest starting time for an activity is equal to the latest finish time minus the duration of the activity.

(True/False)
4.9/5
(34)

The earliest finish time for an activity is equal to the latest finish time minus the activity slack.

(True/False)
4.8/5
(34)

There are four activities on the critical path.Coincidentally,their standard deviations are all equal to 4.The standard deviation of the critical path is therefore equal to:

(Multiple Choice)
4.7/5
(41)

An immediate predecessor of an activity must be completed before that activity can begin.

(True/False)
4.9/5
(42)

Figure Figure   Given this network: -The critical path for the network shown is: Given this network: -The critical path for the network shown is:

(Multiple Choice)
4.9/5
(36)

Figure Figure   Given this network: -The expected duration of this project is: Given this network: -The expected duration of this project is:

(Multiple Choice)
4.9/5
(36)
Showing 81 - 93 of 93
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)