Exam 19: CD - Pertcpm Models for Project Management
Exam 1: Introduction28 Questions
Exam 2: Linear Programming: Basic Concepts83 Questions
Exam 3: Linear Programming: Formulation and Applications58 Questions
Exam 4: The Art of Modeling With Spreadsheets31 Questions
Exam 5: What-If Analysis for Linear Programming63 Questions
Exam 6: Network Optimization Problems48 Questions
Exam 7: Using Binary Integer Programming to Deal With Yes-Or-No Decisions26 Questions
Exam 8: Nonlinear Programming53 Questions
Exam 9: Decision Analysis77 Questions
Exam 10: Cd Supplement - Decision Analysis26 Questions
Exam 11: Forecasting76 Questions
Exam 12: Queueing Models75 Questions
Exam 13: CD Supplement - Additional Queueing Models8 Questions
Exam 14: Computer Simulation: Basic Concepts45 Questions
Exam 15: CD Supplement - the Inverse Transformation Method for Generating Random Observations2 Questions
Exam 16: Computer Simulation With Crystal Ball53 Questions
Exam 17: CD - Solution Concepts for Linear Programming45 Questions
Exam 18: CD - Transportation and Assignment Problems48 Questions
Exam 19: CD - Pertcpm Models for Project Management93 Questions
Exam 20: CD - Goal Programming21 Questions
Exam 21: CD - Inventory Management With Known Demand64 Questions
Exam 22: CD - Inventory Management With Uncertain Demand43 Questions
Select questions type
Given this information about activity H: ES = 10,EF = 15,LS = 16,and LF = 21,we can determine that the amount of slack associated with the activity is:
(Multiple Choice)
4.7/5
(35)
A project manager does not need to monitor each individual activity,just the overall project when looking at budget costs.
(True/False)
4.7/5
(28)
In a project network the critical path is the sequence of activities which has:
(Multiple Choice)
4.7/5
(42)
Figure
Given this network:
-The expected duration of this project is:

(Multiple Choice)
4.8/5
(37)
An activity in a project network cannot begin until all of the activities leading into that activity have been completed.
(True/False)
4.7/5
(32)
In crashing a project,a manager will generally focus on activities which:
(Multiple Choice)
4.8/5
(36)
The latest starting time for an activity is equal to the latest finish time minus the duration of the activity.
(True/False)
4.9/5
(34)
The earliest finish time for an activity is equal to the latest finish time minus the activity slack.
(True/False)
4.8/5
(34)
There are four activities on the critical path.Coincidentally,their standard deviations are all equal to 4.The standard deviation of the critical path is therefore equal to:
(Multiple Choice)
4.7/5
(41)
An immediate predecessor of an activity must be completed before that activity can begin.
(True/False)
4.9/5
(42)
Figure
Given this network:
-The critical path for the network shown is:

(Multiple Choice)
4.9/5
(36)
Figure
Given this network:
-The expected duration of this project is:

(Multiple Choice)
4.9/5
(36)