Exam 19: CD - Pertcpm Models for Project Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Figure Figure   (time in days) -What is the estimated standard deviation in the time for activity E? (time in days) -What is the estimated standard deviation in the time for activity E?

Free
(Multiple Choice)
4.8/5
(31)
Correct Answer:
Verified

B

In PERT,the project duration will never exceed the expected duration of the critical path.

Free
(True/False)
4.8/5
(43)
Correct Answer:
Verified

False

The sum of durations of the longest path in a project network indicates expected project completion time,and the activities are the critical activities.

Free
(True/False)
4.9/5
(41)
Correct Answer:
Verified

True

  Given the portion of the network shown above,what is the latest start time of activity D if the latest finish of activity F is 26 and the latest finish of activity G is 23? Given the portion of the network shown above,what is the latest start time of activity D if the latest finish of activity F is 26 and the latest finish of activity G is 23?

(Multiple Choice)
4.9/5
(33)

Figure Figure   (time in days) -What is the estimated mean time for project completion? (time in days) -What is the estimated mean time for project completion?

(Multiple Choice)
4.7/5
(36)

Figure Figure   (time in days) -What is the estimated mean time for project completion? (time in days) -What is the estimated mean time for project completion?

(Multiple Choice)
4.8/5
(33)

The earliest finish time for an activity is equal to the latest finish time minus the duration of the activity.

(True/False)
5.0/5
(33)

Figure Figure   -The path with the greatest slack is: -The path with the greatest slack is:

(Multiple Choice)
4.9/5
(40)

The slack of an activity is the difference between the latest finish and the earliest finish times.

(True/False)
4.8/5
(36)

The project management strategy of injecting additional resources in order to reduce the length of the project is called:

(Multiple Choice)
4.8/5
(34)

Figure Figure   (time in days) -What is the probability that the critical path will be completed within 200 days? (time in days) -What is the probability that the critical path will be completed within 200 days?

(Multiple Choice)
4.8/5
(39)

PERT/Cost can be used to monitor budget overruns.

(True/False)
4.9/5
(37)

The project network diagram describes sequential relationships among major activities in a project.

(True/False)
4.7/5
(37)

The standard deviation of a path is computed as:

(Multiple Choice)
4.9/5
(35)

PERT/Cost is a systematic procedure to help a project manager bid on a project.

(True/False)
4.9/5
(24)

The activities with the longest durations in a project network are called critical activities.

(True/False)
4.8/5
(25)

When using linear programming to make crashing decisions,the objective is to minimize:

(Multiple Choice)
4.9/5
(40)

The earliest start of an activity is the latest early finish of any immediately preceding activity.

(True/False)
4.9/5
(35)

The earliest start time for an activity is:

(Multiple Choice)
4.8/5
(37)

At which point does crashing of a project cease?

(Multiple Choice)
4.9/5
(36)
Showing 1 - 20 of 93
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)