Exam 19: CD - Pertcpm Models for Project Management
Exam 1: Introduction28 Questions
Exam 2: Linear Programming: Basic Concepts83 Questions
Exam 3: Linear Programming: Formulation and Applications58 Questions
Exam 4: The Art of Modeling With Spreadsheets31 Questions
Exam 5: What-If Analysis for Linear Programming63 Questions
Exam 6: Network Optimization Problems48 Questions
Exam 7: Using Binary Integer Programming to Deal With Yes-Or-No Decisions26 Questions
Exam 8: Nonlinear Programming53 Questions
Exam 9: Decision Analysis77 Questions
Exam 10: Cd Supplement - Decision Analysis26 Questions
Exam 11: Forecasting76 Questions
Exam 12: Queueing Models75 Questions
Exam 13: CD Supplement - Additional Queueing Models8 Questions
Exam 14: Computer Simulation: Basic Concepts45 Questions
Exam 15: CD Supplement - the Inverse Transformation Method for Generating Random Observations2 Questions
Exam 16: Computer Simulation With Crystal Ball53 Questions
Exam 17: CD - Solution Concepts for Linear Programming45 Questions
Exam 18: CD - Transportation and Assignment Problems48 Questions
Exam 19: CD - Pertcpm Models for Project Management93 Questions
Exam 20: CD - Goal Programming21 Questions
Exam 21: CD - Inventory Management With Known Demand64 Questions
Exam 22: CD - Inventory Management With Uncertain Demand43 Questions
Select questions type
Figure
(time in days)
-What is the estimated standard deviation in the time for activity E?

Free
(Multiple Choice)
4.8/5
(31)
Correct Answer:
B
In PERT,the project duration will never exceed the expected duration of the critical path.
Free
(True/False)
4.8/5
(43)
Correct Answer:
False
The sum of durations of the longest path in a project network indicates expected project completion time,and the activities are the critical activities.
Free
(True/False)
4.9/5
(41)
Correct Answer:
True
Given the portion of the network shown above,what is the latest start time of activity D if the latest finish of activity F is 26 and the latest finish of activity G is 23?

(Multiple Choice)
4.9/5
(33)
Figure
(time in days)
-What is the estimated mean time for project completion?

(Multiple Choice)
4.7/5
(36)
Figure
(time in days)
-What is the estimated mean time for project completion?

(Multiple Choice)
4.8/5
(33)
The earliest finish time for an activity is equal to the latest finish time minus the duration of the activity.
(True/False)
5.0/5
(33)
The slack of an activity is the difference between the latest finish and the earliest finish times.
(True/False)
4.8/5
(36)
The project management strategy of injecting additional resources in order to reduce the length of the project is called:
(Multiple Choice)
4.8/5
(34)
Figure
(time in days)
-What is the probability that the critical path will be completed within 200 days?

(Multiple Choice)
4.8/5
(39)
The project network diagram describes sequential relationships among major activities in a project.
(True/False)
4.7/5
(37)
PERT/Cost is a systematic procedure to help a project manager bid on a project.
(True/False)
4.9/5
(24)
The activities with the longest durations in a project network are called critical activities.
(True/False)
4.8/5
(25)
When using linear programming to make crashing decisions,the objective is to minimize:
(Multiple Choice)
4.9/5
(40)
The earliest start of an activity is the latest early finish of any immediately preceding activity.
(True/False)
4.9/5
(35)