Exam 19: CD - Pertcpm Models for Project Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Crashing cannot be accomplished by using different materials than originally planned.

(True/False)
4.8/5
(32)

When finding the approximate probability of project duration,it is necessary to know which of the following?

(Multiple Choice)
4.8/5
(33)

Figure Figure   (time in days) -What is the estimated slack time for activity W? (time in days) -What is the estimated slack time for activity W?

(Multiple Choice)
4.9/5
(32)

The mean critical path is the path through the project network that would be the critical path if the duration of each activity equals its mean.

(True/False)
4.7/5
(42)

Figure Figure   Given this network: -The path with the greatest slack is: Given this network: -The path with the greatest slack is:

(Multiple Choice)
4.8/5
(30)

The PERT three-estimate approach can be used to determine the probability that a project will be completed by a certain time.

(True/False)
4.9/5
(32)

Figure Figure   Given this network: -The critical path for the network shown is: Given this network: -The critical path for the network shown is:

(Multiple Choice)
4.8/5
(30)

Figure Figure   (time in days) -What is the probability that the critical path will be completed within 210 days? (time in days) -What is the probability that the critical path will be completed within 210 days?

(Multiple Choice)
4.8/5
(32)

If an activity is not on the critical path,then the project cannot be delayed if that activity is delayed.

(True/False)
4.9/5
(39)

Activities that are not on the critical path have a slack time equal to zero.

(True/False)
4.9/5
(31)

Figure Figure   (time in days) -What is the estimated mean time for activity Y? (time in days) -What is the estimated mean time for activity Y?

(Multiple Choice)
4.7/5
(37)

Figure Figure   (time in days) -What is the estimated standard deviation in the time for activity E? (time in days) -What is the estimated standard deviation in the time for activity E?

(Multiple Choice)
4.8/5
(34)

There is currently no method that permits activities and their immediate predecessors to overlap. Multiple Choice Questions

(True/False)
4.7/5
(39)

Crashing an activity will always reduce the duration of a project.

(True/False)
5.0/5
(40)

Figure Figure   (time in days) -What is the estimated slack time for activity D? (time in days) -What is the estimated slack time for activity D?

(Multiple Choice)
4.8/5
(31)

When making a backward pass through a project network,you must start at the finish node.

(True/False)
4.9/5
(35)

Figure Figure   Given this network: -The slack for path A-D-H-I is: Given this network: -The slack for path A-D-H-I is:

(Multiple Choice)
4.7/5
(45)

  Given the portion of the network shown above,what is the earliest finish time for activity D,if the earliest start time of A is 12 and the earliest start time of B is 13? Given the portion of the network shown above,what is the earliest finish time for activity D,if the earliest start time of A is 12 and the earliest start time of B is 13?

(Multiple Choice)
4.8/5
(28)

The slack of any activity is the amount of time that the activity can be delayed without delaying the completion of the project.

(True/False)
4.7/5
(37)

An activity has an optimistic time estimate of three days,a most likely time estimate of eight days,and a pessimistic time estimate of ten days.The expected duration of this activity is:

(Multiple Choice)
4.7/5
(27)
Showing 21 - 40 of 93
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)