Exam 15: Waiting Line Models
Exam 1: Introduction61 Questions
Exam 2: Introduction to Probability66 Questions
Exam 3: Probability Distributions66 Questions
Exam 4: Decision Analysis64 Questions
Exam 5: Utility and Game Theory67 Questions
Exam 6: Times Series Analysis and Forecasting63 Questions
Exam 7: Introduction to Linear Programming60 Questions
Exam 8: Linear Programming: Sensitivity Analysis and Interpretation of Solution64 Questions
Exam 9: Linear Programming Applications in Marketing, Finance, and Operations Management60 Questions
Exam 10: Distribution and Network Models67 Questions
Exam 11: Integer Linear Programming61 Questions
Exam 12: Advanced Optimization Applications56 Questions
Exam 13: Project Scheduling: Pertcpm66 Questions
Exam 14: Inventory Models66 Questions
Exam 15: Waiting Line Models62 Questions
Exam 16: Simulation62 Questions
Exam 17: Markov Processes55 Questions
Select questions type
The insurance department at Shear's has two agents,each working at a mean speed of 8 customers per hour.Customers arrive at the insurance desk at a mean rate of one every six minutes and form a single queue.Management feels that some customers are going to find the wait at the desk too long and take their business to Word's,Shear's competitor.
In order to reduce the time required by an agent to serve a customer Shear's is contemplating installing one of two minicomputer systems: System A which leases for $18 per day and will increase an agent's efficiency by 25%; or,System B which leases for $23 per day and will increase an agent's efficiency by 50%.Agents work 8-hour days.
If Shear's estimates its cost of having a customer in the system at $3 per hour,determine if Shear's should install a new minicomputer system,and if so,which one.
(Essay)