Exam 14: Materials and Resource Requirements Planning

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Materials requirement planning (MRP) systems are used primarily to:

(Multiple Choice)
4.8/5
(33)

Using the BOM, if 2 units of A are needed, how many used of K will be required? Assume that there is no on-hand inventory of any items. Using the BOM, if 2 units of A are needed, how many used of K will be required? Assume that there is no on-hand inventory of any items.

(Multiple Choice)
4.9/5
(40)

End item A is made by assembling 2 of part B and 3 of part C. Part C is made from 2 of component D and 2 of component E. Component D is considered to be a:

(Multiple Choice)
4.9/5
(33)

The following table shows capacity requirements data for making table tops. The following table shows capacity requirements data for making table tops.   Which of the following is TRUE? Which of the following is TRUE?

(Multiple Choice)
4.8/5
(43)

The longest lead time path in the BOM is the:

(Multiple Choice)
4.9/5
(33)

Constant changing of the master schedule and the resulting changes in the requirements for components is referred to as:

(Multiple Choice)
4.9/5
(36)

Advanced planning and scheduling systems:

(Multiple Choice)
4.9/5
(31)

Rough-cut capacity planning does all of the following EXCEPT:

(Multiple Choice)
4.8/5
(38)

Zanda Company is looking for a requirements planning system to help plan replenishment of its finished goods throughout its network of distribution centers. The type of system Zanda should consider is known as:

(Multiple Choice)
4.8/5
(42)