Exam 18: Project Management
Exam 1: Goods, Services, and Operations Management65 Questions
Exam 2: Value Chains68 Questions
Exam 3: Measuring Performance in Operations81 Questions
Exam 4: Operations Strategy65 Questions
Exam 5: Technology and Operations Management72 Questions
Exam 6: Goods and Service Design91 Questions
Exam 7: Process Selection, Design, and Analysis89 Questions
Exam 8: Facility and Work Design79 Questions
Exam 9: Supply Chain Design71 Questions
Exam 10: Capacity Management70 Questions
Exam 11: Forecasting and Demand Planning76 Questions
Exam 12: Managing Inventories89 Questions
Exam 13: Resource Management82 Questions
Exam 14: Operations Scheduling and Sequencing65 Questions
Exam 15: Quality Management73 Questions
Exam 16: Quality Control and Spc85 Questions
Exam 17: Lean Operating Systems63 Questions
Exam 18: Project Management60 Questions
Select questions type
Which of the following is incorrect regarding time/cost trade-offs?
Free
(Multiple Choice)
4.8/5
(33)
Correct Answer:
D
The network below represents a project being analyzed by the Critical Path Method.
a.What activity must be on the critical path, regardless of activity durations?
b.What is the duration of path A-B-E-H-J?
c.What is the critical path of this network?
d.What is the length of the critical path?

Free
(Essay)
4.7/5
(36)
Correct Answer:
a.A
b.20
c.A, B, G, I, J
d.30
Because the preparation of annual reports is done on a repeating basis, project management techniques are not appropriate.
Free
(True/False)
4.9/5
(39)
Correct Answer:
False
Data regarding the activities for a project are presented below. The times are in weeks. The critical path for this project is A - D - H - I - J - K.
a.Determine the standard deviation of the critical path.
b.Determine the probability of completing the project in 38 weeks or less.
c.What is the probability of completing the project in 32 weeks or less?

(Essay)
4.9/5
(30)
Describe how a project fits into each of the three common organizational structures.
(Essay)
4.7/5
(37)
Strong leadership is an impediment to project management success because of the team-based nature of most projects.
(True/False)
4.9/5
(33)
You are in charge of the "advertising program" for the Boston Red Sox baseball team during their spring training in Fort Myers, Florida. You have defined the advertising program as a project with the following characteristics. The goal is to fill all stadium seats during the spring training season.
a.What is the earliest completion time for this project?
b.What is the largest amount of slack that any activity has in this project?
c.If activity C is delayed three weeks, what is the revised earliest project completion time?
d.For the original CPM problem, what is the minimum number of activities that would have to be crashed in order to reduce the project's earliest completion time by two weeks assuming all activity crash costs per week are the same and all activities can be crashed?

(Essay)
4.9/5
(36)
Which statement is true regarding activities not on the critical path?
(Multiple Choice)
4.9/5
(43)
Which of the following is least related to Program Evaluation and Review Technique (PERT)?
(Multiple Choice)
4.7/5
(32)
With the Activity-On-Node (AON) network, the nodes define the precedence relationships and the arcs define the work activities.
(True/False)
4.8/5
(35)
In which stage in the project life cycle would critical path calculations be performed?
(Multiple Choice)
4.8/5
(34)
Explain the three time estimates used to characterize uncertainty of activity times in the Program Evaluation and Review Technique (PERT) procedure.
(Essay)
4.9/5
(28)
Describe the four major steps in the project-planning process.
(Short Answer)
4.8/5
(37)
Which step in the project management process would involve developing alternative plans in anticipation of problems that might arise?
(Multiple Choice)
4.9/5
(37)
A company has used PERT for a project and wants to minimize the probability of overrunning a contract deadline of 30 weeks. Three paths of concern in the PERT network have these mean durations and variances in weeks:
a.What is the Z-score for path 1?
b.What is the probability of path 2 overrunning the deadline?

(Essay)
4.9/5
(32)
When finding the earliest finish (EF) time for an activity with two or more predecessor activities, the largest EF among the predecessor activities is used to calculate the EF for that activity.
(True/False)
4.9/5
(40)
Define a project. Give some non-manufacturing or non-construction examples.
(Essay)
4.8/5
(37)
A type of organization which "loans" resources to projects while still maintaining control over them is called
(Multiple Choice)
4.7/5
(32)
The early start time for an activity is computed by finding the largest early finish time of all immediate predecessors.
(True/False)
4.9/5
(38)
Showing 1 - 20 of 60