Exam 13: Project Scheduling: Pertcpm

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Consider a project that has been modeled as follows: Consider a project that has been modeled as follows:     a.Draw the PERT/CPM network for this project and determine project's expected completion time and its critical path. b.Can activities E and G be performed simultaneously without delaying the minimum project completion time? c.Can one person perform A,G,and I without delaying the project? d.By how much can activities G and L be delayed without delaying the entire project? e.How much would the project be delayed if activity G was delayed by 7 hours and activity L was delayed by 4 hours? Explain. a.Draw the PERT/CPM network for this project and determine project's expected completion time and its critical path. b.Can activities E and G be performed simultaneously without delaying the minimum project completion time? c.Can one person perform A,G,and I without delaying the project? d.By how much can activities G and L be delayed without delaying the entire project? e.How much would the project be delayed if activity G was delayed by 7 hours and activity L was delayed by 4 hours? Explain.

(Essay)
4.9/5
(38)

The critical path

(Multiple Choice)
5.0/5
(42)

Arcs in a project network indicate

(Multiple Choice)
4.8/5
(32)

When activity times are uncertain,total project time is normally distributed with mean equal to the sum of the means of all of the critical activities.

(True/False)
4.8/5
(27)

In deciding which activities to crash,one must

(Multiple Choice)
4.7/5
(35)

The latest finish time for an activity is the largest of the latest start times for all activities that immediately follow the activity.

(True/False)
4.8/5
(42)

To determine how to crash activity times

(Multiple Choice)
4.9/5
(38)

When activity times are uncertain,

(Multiple Choice)
4.9/5
(43)

PERT and CPM

(Multiple Choice)
4.8/5
(40)

The earliest finish time for the final activity is the project duration.

(True/False)
4.9/5
(41)

A critical activity can be part of a noncritical path.

(True/False)
4.9/5
(33)

The length of time an activity can be delayed without affecting the project completion time is the slack.

(True/False)
4.9/5
(41)

Activities G,P,and R are the immediate predecessors for activity W.If the earliest finish times for the three are 12,15,and 10,then the earliest start time for W

(Multiple Choice)
4.9/5
(34)

Which of the following is always true about a critical activity?

(Multiple Choice)
4.8/5
(35)

Consider the following PERT/CPM network with estimated times in weeks.The project is scheduled to begin on May 1. Consider the following PERT/CPM network with estimated times in weeks.The project is scheduled to begin on May 1.   The three-time estimate approach was used to calculate the expected times and the following table gives the variance for each activity:     a.Give the expected project completion date and the critical path. b.By what date are you 99% sure the project will be completed? The three-time estimate approach was used to calculate the expected times and the following table gives the variance for each activity: Consider the following PERT/CPM network with estimated times in weeks.The project is scheduled to begin on May 1.   The three-time estimate approach was used to calculate the expected times and the following table gives the variance for each activity:     a.Give the expected project completion date and the critical path. b.By what date are you 99% sure the project will be completed? a.Give the expected project completion date and the critical path. b.By what date are you 99% sure the project will be completed?

(Essay)
4.8/5
(35)

Activities K,M and S immediately follow activity H,and their latest start times are 14,18,and 11.The latest finish time for activity H

(Multiple Choice)
4.9/5
(36)

Which of the following is a general rule for crashing activities?

(Multiple Choice)
4.8/5
(32)

The earliest start time for an activity is equal to the smallest of the earliest finish times for all its immediate predecessors.

(True/False)
4.8/5
(37)

When activity times are uncertain,an activity's most likely time is the same as its expected time.

(True/False)
4.9/5
(28)

Crashing refers to an unanticipated delay in a critical path activity that causes the total time to exceed its limit.

(True/False)
4.9/5
(32)
Showing 21 - 40 of 41
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)