Exam 13: Project Scheduling: Pertcpm
Exam 1: Introduction50 Questions
Exam 2: Introduction to Probability53 Questions
Exam 3: Probability Distributions52 Questions
Exam 4: Decision Analysis48 Questions
Exam 5: Utility and Game Theory49 Questions
Exam 6: Forecasting60 Questions
Exam 7: Introduction to Linear Programming54 Questions
Exam 8: Lp Sensitivity Analysis and Interpretation of Solution49 Questions
Exam 9: Linear Programming Applications42 Questions
Exam 10: Distribution and Network Problems57 Questions
Exam 11: Integer Linear Programming49 Questions
Exam 12: Advanced Optimization Application42 Questions
Exam 13: Project Scheduling: Pertcpm41 Questions
Exam 14: Inventory Models54 Questions
Exam 15: Waiting Line Models52 Questions
Exam 16: Simulation49 Questions
Exam 17: Markov Processes44 Questions
Select questions type
Consider a project that has been modeled as follows:
a.Draw the PERT/CPM network for this project and determine project's expected completion time and its critical path.
b.Can activities E and G be performed simultaneously without delaying the minimum project completion time?
c.Can one person perform A,G,and I without delaying the project?
d.By how much can activities G and L be delayed without delaying the entire project?
e.How much would the project be delayed if activity G was delayed by 7 hours and activity L was delayed by 4 hours? Explain.

(Essay)
4.9/5
(38)
When activity times are uncertain,total project time is normally distributed with mean equal to the sum of the means of all of the critical activities.
(True/False)
4.8/5
(27)
The latest finish time for an activity is the largest of the latest start times for all activities that immediately follow the activity.
(True/False)
4.8/5
(42)
The earliest finish time for the final activity is the project duration.
(True/False)
4.9/5
(41)
The length of time an activity can be delayed without affecting the project completion time is the slack.
(True/False)
4.9/5
(41)
Activities G,P,and R are the immediate predecessors for activity W.If the earliest finish times for the three are 12,15,and 10,then the earliest start time for W
(Multiple Choice)
4.9/5
(34)
Which of the following is always true about a critical activity?
(Multiple Choice)
4.8/5
(35)
Consider the following PERT/CPM network with estimated times in weeks.The project is scheduled to begin on May 1.
The three-time estimate approach was used to calculate the expected times and the following table gives the variance for each activity:
a.Give the expected project completion date and the critical path.
b.By what date are you 99% sure the project will be completed?


(Essay)
4.8/5
(35)
Activities K,M and S immediately follow activity H,and their latest start times are 14,18,and 11.The latest finish time for activity H
(Multiple Choice)
4.9/5
(36)
Which of the following is a general rule for crashing activities?
(Multiple Choice)
4.8/5
(32)
The earliest start time for an activity is equal to the smallest of the earliest finish times for all its immediate predecessors.
(True/False)
4.8/5
(37)
When activity times are uncertain,an activity's most likely time is the same as its expected time.
(True/False)
4.9/5
(28)
Crashing refers to an unanticipated delay in a critical path activity that causes the total time to exceed its limit.
(True/False)
4.9/5
(32)
Showing 21 - 40 of 41
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)