Exam 20: Master Scheduling and Rough-Cut Capacity Planning

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Consider the following partial MPS record. Beginning inventory is 70 units. The firm uses an order quantity of POQ = 2 periods. Fill out the last two rows of the table. Consider the following partial MPS record. Beginning inventory is 70 units. The firm uses an order quantity of POQ = 2 periods. Fill out the last two rows of the table.

(Essay)
4.8/5
(36)

The projected available quantity row in an MPS record keeps track of how many units are available at the beginning of each time period.

(True/False)
4.9/5
(29)

In future periods, MPS Shipments - Customer orders between current and next scheduled MPS shipment is called ________________________.

(Short Answer)
4.7/5
(35)

When Projected Available is negative, the Master Production Schedule must include ________________________.

(Short Answer)
4.8/5
(35)

A negative number in the projected available row is ___________ a problem.

(Multiple Choice)
4.8/5
(34)

Which of the following is not part of the process for developing an MPS?

(Multiple Choice)
5.0/5
(37)

Demand management includes all but which of the following:

(Multiple Choice)
4.7/5
(36)

Which of the following is not a correctly stated step of the CPOPF method?

(Multiple Choice)
4.9/5
(28)

Which of the following is not a correctly stated step of the CPOPF method?

(Multiple Choice)
4.9/5
(42)