Exam 20: Master Scheduling and Rough-Cut Capacity Planning

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Discuss the Master scheduler responsibility.

(Essay)
4.7/5
(35)

To evaluate the MPS in terms of customer service, the master scheduler checks that:

(Multiple Choice)
4.8/5
(35)

What is the formula for calculating the ATP quantity at future replenishment periods?

(Multiple Choice)
4.9/5
(28)

Consider the following partial ATP MPS record. Beginning inventory is 40 units. The firm uses a fixed order quantity of 70 units. What is the projected available amount in period 2? Consider the following partial ATP MPS record. Beginning inventory is 40 units. The firm uses a fixed order quantity of 70 units. What is the projected available amount in period 2?

(Multiple Choice)
4.7/5
(39)

Consider the following partial MPS record. Beginning inventory is 60 units. When should the first MPS shipment be scheduled? Consider the following partial MPS record. Beginning inventory is 60 units. When should the first MPS shipment be scheduled?

(Multiple Choice)
5.0/5
(32)

What is the portion of the MPS called that lies between the current time and the demand time fence?

(Multiple Choice)
4.9/5
(29)

What term refers to proven capacity calculated from actual performance data?

(Multiple Choice)
4.8/5
(37)

The MPS available-to-promise row shows:

(Multiple Choice)
4.9/5
(35)

What data are added to create an extended MPS record that allows the firm to compute available-to-promise units?

(Multiple Choice)
4.8/5
(31)

The ______ _____ shows how many products or services are planned for each time period.

(Short Answer)
4.8/5
(32)

A primary objective of the master production schedule is to achieve the desired customer service level.

(True/False)
4.9/5
(35)

Consider the following partial MPS record. Beginning inventory is 80 units. When should the first MPS shipment be scheduled? Consider the following partial MPS record. Beginning inventory is 80 units. When should the first MPS shipment be scheduled?

(Multiple Choice)
5.0/5
(34)

Consider the following partial MPS record. Beginning inventory is 100 units. When should the first MPS shipment be scheduled? Consider the following partial MPS record. Beginning inventory is 100 units. When should the first MPS shipment be scheduled?

(Multiple Choice)
4.7/5
(41)

Johnny Now, Inc. produces two different models of outhouses. Demand next period is expected to be 12,000 and 18,000 units for Models A and B, respectively. Model A has CPOPF planning factors of 0.75 and 0.60 for direct labor and machine time, respectively. Model B has CPOPF planning factors of 0.50 and 0.80 for direct labor and machine time, respectively. Historically department G uses 24% of the direct labor and machine time for these products, while department H uses the remaining 76%. What is the direct labor time requirement for department G next period?

(Multiple Choice)
4.8/5
(31)

The available-to-promise row in an extended MPS record shows how many committed units the company has available for delivery at a given time.

(True/False)
4.9/5
(32)

What is the portion of the MPS called that lies between the demand time fence and the planning time fence?

(Multiple Choice)
4.8/5
(38)

In the "slushy" portion of the MPS, changes in the product mix are possible, but changes needing additional resources are not.

(True/False)
4.8/5
(43)

Engines Corp. builds two different types of motors in three departments. Historically, department X uses 20%, department Y uses 50%, and department Z uses 30% of direct labor and machine time, respectively. In the next quarter, demand for Model A is expected to be 40,000 units, and demand for Model B is expected to be for 50,000 units. The CPOPF planning factors are: direct labor for Model A = 0.667 hrs./unit, machine time for Model A = 1.75 hrs./unit, direct labor for Model B = 1.087 hrs./unit, machine time for Model B = 0.261 hrs./unit. Calculate the amount of labor and machine time that will need to be allocated to each of the three departments next quarter.

(Essay)
4.7/5
(32)

In the "liquid" portion of the MPS, the master scheduler generally has the authority to approve what changes?

(Multiple Choice)
4.8/5
(34)

The MPS is said to be ________________________ between final assembly and cumulative manufacturing lead times.

(Short Answer)
4.8/5
(43)
Showing 41 - 60 of 69