Exam 14: Project Management Information Systems
Exam 1: Project Management Concepts74 Questions
Exam 2: Identifying and Selecting Projects70 Questions
Exam 3: Developing Project Proposals111 Questions
Exam 4: Defining Scope, Quality, Responsibility, and Activity Sequence129 Questions
Exam 5: Developing the Schedule79 Questions
Exam 6: Resource Utilization21 Questions
Exam 7: Determining Costs, Budget, and Earned Value69 Questions
Exam 8: Managing Risk45 Questions
Exam 9: Closing the Project42 Questions
Exam 10: The Project Manager129 Questions
Exam 11: The Project Team225 Questions
Exam 12: Project Communication and Documentation121 Questions
Exam 13: Project Management Organizational Structures65 Questions
Exam 14: Project Management Information Systems46 Questions
Select questions type
An advantage of a project management information system is the speed because calculations and revisions can typically be performed in seconds.
(True/False)
4.8/5
(48)
A critically important, feature in project management information systems is __________ features because some systems provide password access to the project management program itself, password access to individual project files, and password access to specific data within a project file.
(Multiple Choice)
4.9/5
(36)
A concern to be considered about a project management information system is the ________. Project managers have to resist the temptation to use features that produce more reports or more data without contributing to the successful completion of the project.
(Multiple Choice)
4.8/5
(37)
A concern to be considered about a project management information system is the _______. Project managers might believe that, because they have a powerful project management information system, they can manage and accomplish more than is actually feasible. Managers might think that, although a project is slipping, the system will be able to figure out a way to get it back on track. Just because the system says everything is all right doesn't necessarily make it so.
(Multiple Choice)
4.9/5
(34)
________ are uncertain events or circumstances that could have an impact on a project.
(Multiple Choice)
4.8/5
(35)
_______ features of most systems that are available to help include approval process and routing, change order management, contract management and automation, meeting management and action items, project charter information, requirements management, and time-off requests.
(Multiple Choice)
4.9/5
(35)
Showing 41 - 46 of 46