Exam 5: Developing the Schedule

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

It is necessary to monitor the progress to ensure that everything is going according to the plan.

(True/False)
4.7/5
(36)

Calculate the earliest finish for Task B if its predecessor, Task A, finishes on day 3 and the duration of Task B is 2 days.

(Multiple Choice)
4.7/5
(35)

The estimated duration for each activity is indicated by a bar spanning the period

(Multiple Choice)
4.9/5
(38)

The total completion time is 25 days. Task A is planned to take seven days. Task B is planned to take five days. Task C is planned to take eight days. The tasks have a serial relationship. How much slack does the project have?

(Multiple Choice)
4.8/5
(32)

When considering the availability of resources, it may be necessary to make some assumptions, such as

(Multiple Choice)
4.8/5
(38)

Free slack is the amount of time a specific activity can be

(Multiple Choice)
4.8/5
(37)

With respect to the project schedule, changes can result in any of the following except

(Multiple Choice)
4.9/5
(33)

Once this baseline plan is agreed upon by the customer and the contractor or project team, the project work can be performed.

(True/False)
4.9/5
(51)

Total slack for the project is the difference between

(Multiple Choice)
4.8/5
(40)

Free slack is calculated by finding the lowest of the values of total slack for all the activities entering into a specific activity and then

(Multiple Choice)
4.8/5
(42)

Each organization or subcontractor responsible for a group or type of activities should always designate an inexperienced individual to estimate the durations for all the activities for which the organization or subcontractor is responsible.

(True/False)
4.8/5
(40)

In many cases, especially for smaller projects, most activities involve people resources-that is,

(Multiple Choice)
4.8/5
(39)

When the customer requests a change, the contractor or project team should estimate the impact on the project schedule and budget and then go ahead with the work without customer approval.

(True/False)
4.7/5
(37)

A Gantt chart is the often the name for the network diagram tool for planning and scheduling.

(True/False)
4.8/5
(35)

The key to effective project control is measuring actual progress and comparing it to planned progress on a timely and regular basis and

(Multiple Choice)
4.8/5
(36)

A consistent time base, such as hours or days or weeks, should be used for all the estimated durations of activities in a network diagram.

(True/False)
4.7/5
(32)

The estimated duration for an activity must be based on the estimated quantity of resources required to perform the activity.

(True/False)
4.8/5
(38)

Calculate the latest start for Task D if one of its successors, Task F, has a latest start on day 9, its other successor, Task E, has a latest start on day 10, and the duration of Task D is 2 days.

(Multiple Choice)
4.9/5
(36)

Total slack is calculated for each of the activities by finding the difference between

(Multiple Choice)
4.9/5
(29)

Calculate the latest start for Task B if its predecessor, Task A, finishes on day 3, its succeeding activity, Task E, has a latest start of day 7, and the duration of Task B is 2 days.

(Multiple Choice)
4.9/5
(33)
Showing 41 - 60 of 79
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)