Exam 5: Developing the Schedule
Exam 1: Project Management Concepts74 Questions
Exam 2: Identifying and Selecting Projects70 Questions
Exam 3: Developing Project Proposals111 Questions
Exam 4: Defining Scope, Quality, Responsibility, and Activity Sequence129 Questions
Exam 5: Developing the Schedule79 Questions
Exam 6: Resource Utilization21 Questions
Exam 7: Determining Costs, Budget, and Earned Value69 Questions
Exam 8: Managing Risk45 Questions
Exam 9: Closing the Project42 Questions
Exam 10: The Project Manager129 Questions
Exam 11: The Project Team225 Questions
Exam 12: Project Communication and Documentation121 Questions
Exam 13: Project Management Organizational Structures65 Questions
Exam 14: Project Management Information Systems46 Questions
Select questions type
It is necessary to monitor the progress to ensure that everything is going according to the plan.
(True/False)
4.7/5
(36)
Calculate the earliest finish for Task B if its predecessor, Task A, finishes on day 3 and the duration of Task B is 2 days.
(Multiple Choice)
4.7/5
(35)
The estimated duration for each activity is indicated by a bar spanning the period
(Multiple Choice)
4.9/5
(38)
The total completion time is 25 days. Task A is planned to take seven days. Task B is planned to take five days. Task C is planned to take eight days. The tasks have a serial relationship. How much slack does the project have?
(Multiple Choice)
4.8/5
(32)
When considering the availability of resources, it may be necessary to make some assumptions, such as
(Multiple Choice)
4.8/5
(38)
Free slack is the amount of time a specific activity can be
(Multiple Choice)
4.8/5
(37)
With respect to the project schedule, changes can result in any of the following except
(Multiple Choice)
4.9/5
(33)
Once this baseline plan is agreed upon by the customer and the contractor or project team, the project work can be performed.
(True/False)
4.9/5
(51)
Free slack is calculated by finding the lowest of the values of total slack for all the activities entering into a specific activity and then
(Multiple Choice)
4.8/5
(42)
Each organization or subcontractor responsible for a group or type of activities should always designate an inexperienced individual to estimate the durations for all the activities for which the organization or subcontractor is responsible.
(True/False)
4.8/5
(40)
In many cases, especially for smaller projects, most activities involve people resources-that is,
(Multiple Choice)
4.8/5
(39)
When the customer requests a change, the contractor or project team should estimate the impact on the project schedule and budget and then go ahead with the work without customer approval.
(True/False)
4.7/5
(37)
A Gantt chart is the often the name for the network diagram tool for planning and scheduling.
(True/False)
4.8/5
(35)
The key to effective project control is measuring actual progress and comparing it to planned progress on a timely and regular basis and
(Multiple Choice)
4.8/5
(36)
A consistent time base, such as hours or days or weeks, should be used for all the estimated durations of activities in a network diagram.
(True/False)
4.7/5
(32)
The estimated duration for an activity must be based on the estimated quantity of resources required to perform the activity.
(True/False)
4.8/5
(38)
Calculate the latest start for Task D if one of its successors, Task F, has a latest start on day 9, its other successor, Task E, has a latest start on day 10, and the duration of Task D is 2 days.
(Multiple Choice)
4.9/5
(36)
Total slack is calculated for each of the activities by finding the difference between
(Multiple Choice)
4.9/5
(29)
Calculate the latest start for Task B if its predecessor, Task A, finishes on day 3, its succeeding activity, Task E, has a latest start of day 7, and the duration of Task B is 2 days.
(Multiple Choice)
4.9/5
(33)
Showing 41 - 60 of 79
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)