Exam 7: Determining Costs, Budget, and Earned Value
Exam 1: Project Management Concepts74 Questions
Exam 2: Identifying and Selecting Projects70 Questions
Exam 3: Developing Project Proposals111 Questions
Exam 4: Defining Scope, Quality, Responsibility, and Activity Sequence129 Questions
Exam 5: Developing the Schedule79 Questions
Exam 6: Resource Utilization21 Questions
Exam 7: Determining Costs, Budget, and Earned Value69 Questions
Exam 8: Managing Risk45 Questions
Exam 9: Closing the Project42 Questions
Exam 10: The Project Manager129 Questions
Exam 11: The Project Team225 Questions
Exam 12: Project Communication and Documentation121 Questions
Exam 13: Project Management Organizational Structures65 Questions
Exam 14: Project Management Information Systems46 Questions
Select questions type
Calculate the forecasted cost at completion if the total budgeted cost = $10,000, the CEV is $8,000, and the CAC is $4,000.
(Multiple Choice)
4.7/5
(44)
The cost performance index (CPI) is a measure of the cost efficiency with which the project is being performed. If the cumulative earned value is greater than the cumulative actual costs, then
(Multiple Choice)
4.8/5
(46)
Costs related to ___________ are for outsourced work when the project teams or contractors do not have the expertise or resources to do certain project tasks.
(Multiple Choice)
5.0/5
(32)
Large projects would have charge codes for the work package numbers to
(Multiple Choice)
4.8/5
(32)
A second method for determining the forecasted cost at completion assumes that, regardless of the efficiency rate the project or work package has experienced in the past, the work to be performed on the remaining portion of the project or work package will be done according to budget. If the cumulative actual cost is greater than the cumulative earned value, then
(Multiple Choice)
4.7/5
(42)
Once a total budgeted cost has been established for each work package, the second step in the project budgeting process is to
(Multiple Choice)
4.7/5
(37)
A third method for determining the forecasted cost at completion is to re-estimate the costs for all the remaining work to be performed and then add this re-estimate to the cumulative actual cost. If the amount of cumulated actual costs is less than difference between the total budgeted cost and the re-estimate, then
(Multiple Choice)
4.8/5
(35)
As data are collected on _______, including portions of any committed cost, they need to be totaled by work package so that they can be compared to the ________
(Multiple Choice)
4.9/5
(31)
Showing 61 - 69 of 69
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)