Documentation of lessons learned should be done on an ongoing basis throughout the planning and performing phases of the project.

(True/False)
4.8/5
(35)

The project manager should prepare a written performance evaluation of each member of the project team that mentions how each has

(Multiple Choice)
4.9/5
(42)

The project team should wait until the end of the project to capture and document lessons learned.

(True/False)
4.9/5
(35)

Participants of _______ should include the project manager, key project team members, and key representatives of the customer's organization who were involved with the project.

(Multiple Choice)
4.8/5
(39)

The project organization should establish a __________ that includes an easily accessible repository that encourages project managers and teams to retrieve lessons learned and information from previous projects.

(Multiple Choice)
4.9/5
(36)

Projects also can be terminated by the sponsor or customer because the project needs have changed.

(True/False)
4.8/5
(41)

The system should organize information so that it has complex commands to retrieve information by category or subject of lesson learned or by key words.

(True/False)
4.7/5
(31)

Verifying that all payments have been made to any subcontractors, consultants, vendors, or suppliers for any purchased materials or services is completed during the

(Multiple Choice)
4.7/5
(35)

The fourth and final phase of the project life cycle is

(Multiple Choice)
4.7/5
(45)

The process of closing the project involves various actions, including

(Multiple Choice)
4.9/5
(33)

There may be circumstances that require a project to be terminated before it is completed.

(True/False)
4.7/5
(40)

The project manager should schedule the post-project evaluation meeting with the customer or sponsor for a time when the customer is in a position to

(Multiple Choice)
4.8/5
(38)

As part of, or in addition to, the documents in the archive, it can be valuable to create a database of common data elements from past projects in order to analyze and determine if there are trends or correlations that

(Multiple Choice)
4.9/5
(32)

What type of knowledge base system should be established by the project organization?

(Essay)
4.9/5
(37)

The process of closing the project involves various actions, including

(Multiple Choice)
4.7/5
(41)

The process of closing the project involves various actions, including

(Multiple Choice)
4.8/5
(44)

Once all payments have been received and made, the project "books," or accounting records, can be closed, and a financial analysis of the project can be made in which final actual costs are compared to

(Multiple Choice)
4.7/5
(39)

The ________ should prepare a written report of project performance including lessons learned and recommendations.

(Multiple Choice)
4.9/5
(43)

As part of, or in addition to, the documents in the archive, it can be valuable to create a database of common data elements from past projects in order to analyze and determine if there are trends or correlations that could be helpful in bidding, planning, and/or performing future projects.

(True/False)
4.8/5
(36)

The project manager should schedule the meeting immediately following the delivery of the final report rather than waiting for a time when the customer is in a position to really determine whether the project met expectations and achieved the anticipated benefits.

(True/False)
4.8/5
(42)
Showing 21 - 40 of 42