Exam 8: Scheduling

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

In AON diagrams,a(n)__________ is a point where one or more lines (arrows)begin or terminate,commonly used for depicting an event or activity.

(Multiple Choice)
4.9/5
(40)

The line connecting two nodes is referred to as a(n)

(Multiple Choice)
4.7/5
(28)

Which of the following is NOT a software tool commonly used to manage projects,especially in relation to time and cost budgets?

(Multiple Choice)
4.8/5
(41)

The variance of a population is a measure of the population's __________.

(Multiple Choice)
5.0/5
(37)

Slack is also known as __________.

(Multiple Choice)
4.8/5
(39)

__________ is the amount of one factor that must be sacrificed in order to achieve more or less of another factor.

(Multiple Choice)
4.9/5
(35)

A(n)__________ is a specific task or set of tasks that are required by the project,use up resources,and take time to complete.

(Multiple Choice)
4.9/5
(40)

Which of the following is NOT an advantage of a Gantt chart?

(Multiple Choice)
4.9/5
(38)

The _________ was developed by Henry Gantt in 1917.

(Multiple Choice)
4.9/5
(23)

Project task E has the following estimates: (1)optimistic time - 10 days,(2)Pessimistic time - 20 days,and (3)Most likely time - 12 Days.The standard deviation for time using the beta statistical distribution is ________ days.

(Multiple Choice)
4.8/5
(33)

The __________ chart shows planned and actual progress for a number of tasks displayed against a horizontal timescale.

(Multiple Choice)
4.9/5
(44)

In AOA networks,an activity of zero duration is called a(n)________.

(Multiple Choice)
4.9/5
(44)

Task H has duration of 5 days,an early start of 25 days,an early finish of 30 days,a late start of 25 days,and a late finish of 30 days.There are __________ days of slack for task H.

(Multiple Choice)
4.7/5
(39)

A precedent relationship where the completion of a predecessor activity depends on the initiation of a successor activity is called a __________.

(Multiple Choice)
4.8/5
(39)

__________ is one possible way to check the nature and impacts of interactions between probabilistic paths in a network.

(Multiple Choice)
4.9/5
(41)

__________ was developed by the U.S.Navy while the __________ was developed by __________.

(Multiple Choice)
4.7/5
(28)

The use of PERT has declined sharply in recent years because a large majority of project management software __________.

(Multiple Choice)
4.7/5
(36)

It is important to good project management to be __________ in estimating the time required to complete each of the various tasks included in the project.

(Multiple Choice)
4.7/5
(38)

Most commercially available project management software applications use the __________.

(Multiple Choice)
4.7/5
(37)

The authors recommend preparing a schedule for each __________.

(Multiple Choice)
4.8/5
(37)
Showing 21 - 40 of 48
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)