Exam 8: Scheduling
Exam 1: Projects in Contemporary Organizations43 Questions
Exam 2: Strategic Management and Project Selection42 Questions
Exam 3: The Project Manager46 Questions
Exam 4: Negotiation and the Management of Conflict49 Questions
Exam 5: The Project in the Organizational Structure52 Questions
Exam 6: Project Activity Planning42 Questions
Exam 7: Budgeting and Cost Estimation43 Questions
Exam 8: Scheduling48 Questions
Exam 9: Resource Allocation51 Questions
Exam 10: Monitoring and Information Systems55 Questions
Exam 11: Project Control44 Questions
Exam 12: Project Auditing52 Questions
Exam 13: Project Termination46 Questions
Select questions type
The series of connected activities (or intermediate events)between any two events in a network is called __________.
Free
(Multiple Choice)
4.8/5
(37)
Correct Answer:
A
__________ law suggests that work expands to fill the allotted time.
Free
(Multiple Choice)
4.9/5
(27)
Correct Answer:
A
Any time two or more paths of a network come together,the probability of both paths being on time is the product of the probabilities for the individual paths.This scenario is referred to as __________.
Free
(Multiple Choice)
4.8/5
(32)
Correct Answer:
A
Assume that task J has a most likely duration of 20 days,an optimistic duration of 13 days,and a pessimistic duration of 30 days.If the optimistic and pessimistic durations are 95 percent estimates,the standard deviation for task J is ________ days.
(Multiple Choice)
4.9/5
(28)
The authors,when discussing networks,describe a(n)__________ as the result of completing one or more activities.It is an identifiable end state,which does not use any resources,occurring at a particular time.
(Multiple Choice)
4.8/5
(37)
Task F has duration of 10 days and an earliest start date of 20 days.Based on the given data,determine the early finish duration for task F.
(Multiple Choice)
4.8/5
(40)
In a network,if the delay of an activity will delay completion of the project,the activity is called a(n)__________.
(Multiple Choice)
4.9/5
(33)
In CPM(PDM),an activity can be conducted at a normal pace or an expedited pace,known as ________,at a greater cost.
(Multiple Choice)
4.8/5
(40)
The calculation of the standard deviation for the beta distribution is based on the assumption that __________.
(Multiple Choice)
5.0/5
(35)
__________ have a weakness of being difficult to follow when multiple paths exist,but __________ are more helpful in the hands-on task of managing the project.
(Multiple Choice)
4.7/5
(40)
Explain why it is important to evaluate non-critical paths that possess large variances and / or path times that are close to critical in duration.
(Essay)
4.9/5
(44)
The difference between the late start and early start for an activity is called its __________.
(Multiple Choice)
4.7/5
(39)
When using the beta distribution,the denominator of the formula for standard deviation should ________.
(Multiple Choice)
4.9/5
(32)
The arrangement of all activities (and,in some cases,events)in a project arrayed in their logical sequence and represented by arcs and nodes is called a __________.
(Multiple Choice)
4.8/5
(28)
Describe the benefits of forming a network of activity and event relationships that graphically portrays sequential relations between tasks in a project.
(Essay)
4.9/5
(29)
Project task E has the following estimates: (1)optimistic time - 10 days,(2)Pessimistic time - 20 days,and (3)Most likely time - 12 Days.The expected time using the beta statistical distribution is __________ days.
(Multiple Choice)
4.8/5
(28)
Explain the difference between Total Slack and Free Slack in a network.
(Essay)
4.8/5
(27)
The authors define __________ as the time an activity can be delayed without affecting the start time of any successor activity
(Multiple Choice)
4.7/5
(35)