Exam 7: Budgeting and Cost Estimation
Exam 1: Projects in Contemporary Organizations43 Questions
Exam 2: Strategic Management and Project Selection42 Questions
Exam 3: The Project Manager46 Questions
Exam 4: Negotiation and the Management of Conflict49 Questions
Exam 5: The Project in the Organizational Structure52 Questions
Exam 6: Project Activity Planning42 Questions
Exam 7: Budgeting and Cost Estimation43 Questions
Exam 8: Scheduling48 Questions
Exam 9: Resource Allocation51 Questions
Exam 10: Monitoring and Information Systems55 Questions
Exam 11: Project Control44 Questions
Exam 12: Project Auditing52 Questions
Exam 13: Project Termination46 Questions
Select questions type
The advantage of the______ process is that it is generally associated with participative management.
Free
(Multiple Choice)
4.8/5
(39)
Correct Answer:
A
Given a project salary cost of $400,000 per year and forecasted wage increases of 5 percent per year,calculate the nondiscounted total salary cost over a three-year project lifecycle.
Free
(Multiple Choice)
4.8/5
(37)
Correct Answer:
C
The budget process generally begins when the top management invites each division to submit a__________ for the upcoming year.
Free
(Multiple Choice)
4.8/5
(34)
Correct Answer:
A
The authors identify __________ estimation errors as the two types of generic estimation errors.
(Multiple Choice)
4.9/5
(28)
__________ relies on well-known statistical correlations between various factors such as the total cost of a house relative to the square feet of living are a.
(Multiple Choice)
4.9/5
(36)
__________ budgeting aggregates income and expenditures by project or program,often in addition to aggregation by organizational unit or activity.
(Multiple Choice)
4.8/5
(30)
A work element whose cost is fully developed would __________.
(Multiple Choice)
4.8/5
(34)
The pattern of deviations in cost and usage used for exception reporting to management is called __________.
(Multiple Choice)
4.7/5
(30)
Suppose that a person requires eight hours to complete a work element on the first attempt.That person has a learning rate of 90 percent for this work element.This person should require __________ hours to complete this work element on the fourth attempt.
(Multiple Choice)
4.9/5
(32)
A __________ is a plan for allocating resources.The allocation of resources indicates the degree to which different activities of an organization are supported fully.
(Multiple Choice)
5.0/5
(31)
____ are where the defined responses to the risks are detailed,but their amounts are not yet precisely known.
(Multiple Choice)
4.9/5
(29)
Each time the output doubles,the worker hours per unit decrease to a fixed percentage of their previous value.That percentage is called the __________ rate.
(Multiple Choice)
4.8/5
(39)
Suppose that a person requires 60 minutes to complete a work element on the first attempt.On the second attempt,the work element is completed in 48 minutes.The learning rate for this person is __________% for this work element.
a)80
b)60
c)70
d)120
(Short Answer)
4.9/5
(40)
__________ states that adding manpower to a late software project makes it later.
(Multiple Choice)
4.9/5
(39)
Identify the statement that is not correct regarding a project budget.
(Multiple Choice)
4.9/5
(35)
A work element in the project plan requires 50 hours of labor each by four carpenters.The carpenters are paid $15 per hour and incur an overhead rate equal to 80 percent of their direct labor charges.The total cost would be __________ if the carpenters consume 10 percent of the workday performing personal activities.
(Multiple Choice)
4.8/5
(29)
The __________ charge is composed of the costs of senior management,the various data functions,and any other expenses not included in overhead.Often,these charges are a fixed percentage of either the direct costs or the total of all direct and indirect costs.
(Multiple Choice)
4.8/5
(36)