Exam 25: Operations Scheduling
Exam 1: Using Operations to Create Value100 Questions
Exam 2: Process Strategy and Analysis245 Questions
Exam 3: Quality and Performance195 Questions
Exam 4: Capacity Planning108 Questions
Exam 5: Constraint Management136 Questions
Exam 6: Lean Systems164 Questions
Exam 7: Project Management140 Questions
Exam 8: Forecasting150 Questions
Exam 9: Inventory Management207 Questions
Exam 10: Operations Planning and Scheduling149 Questions
Exam 11: Resource Planning125 Questions
Exam 12: Supply Chain Design77 Questions
Exam 13: Supply Chain Logistic Networks114 Questions
Exam 14: Supply Chain Integration111 Questions
Exam 15: Supply Chain Sustainability73 Questions
Exam 16: Decision Making107 Questions
Exam 17: Waiting Lines108 Questions
Exam 18: Special Inventory Models53 Questions
Exam 19: Linear Programming86 Questions
Exam 20: Simulation54 Questions
Exam 21: Financial Analysis55 Questions
Exam 22: Acceptance Sampling Plans87 Questions
Exam 23: Measuring Output Rates106 Questions
Exam 24: Learning Curve Analysis51 Questions
Exam 25: Operations Scheduling120 Questions
Exam 26: Layout36 Questions
Select questions type
Table J.12 The Feast
Janice prepares a medley of pastas for her brother Tony.Each of the pastas must first be rolled and then formed (or in some cases stuffed)before cooking.The required time on each machine in minutes is indicated in the table.
-Janice decides to minimize the average flow time of the pastas using Johnson's rule.Which pasta occupies the middle position of her schedule?

Free
(Multiple Choice)
4.8/5
(34)
Correct Answer:
A
Table J.18
-Use the information Table J.18 and sequence the jobs using the SPT rule.What is the average past due?

Free
(Multiple Choice)
4.8/5
(30)
Correct Answer:
B
Critical ratio (CR)is a single-dimension priority rule.
Free
(True/False)
4.9/5
(37)
Correct Answer:
False
Table J.1
The framing department has six jobs waiting to be processed.It is now time zero.Times are expressed in terms of days.
-Using the information in Table J.1 and the SPT rule,what is the average flow time?

(Multiple Choice)
4.9/5
(31)
________ is the total amount of time required to complete a group of jobs.
(Essay)
4.9/5
(33)
Describe the difference between front office and back office operations from the standpoint of scheduling customer jobs.
(Essay)
5.0/5
(34)
Table J.6
All of the following three jobs just arrived (end of hour 0)at Workstation A.They are the only ones waiting to be processed.
-Use the information in Table J.6.What is the average past due time at Workstation A for the critical ratio rule?

(Multiple Choice)
4.9/5
(27)
Table J.1
The framing department has six jobs waiting to be processed.It is now time zero.Times are expressed in terms of days.
-Using the information in Table J.1 and the EDD rule,what is the average flow time?

(Multiple Choice)
4.8/5
(32)
Use the information in the table and sequence the six jobs using the slack per remaining operation algorithm.Calculate the average flow times and average lateness.All jobs arrived at time zero and are ready at time zero.


(Essay)
4.8/5
(31)
Acme has an overabundance of machinery available,but most of the workforce has called in sick after the local team's devastating loss on Monday Night Football.This scheduling problem is a labor-limited environment.
(True/False)
4.8/5
(37)
A(n)________ specializes in low- to medium-volume production using job or batch processes.
(Essay)
4.8/5
(32)
Operations scheduling applies only to manufacturing,because services do not allow inventories.
(True/False)
4.8/5
(37)
The earliest due date (EDD)rule gives the job with the shortest processing time the highest priority.
(True/False)
4.8/5
(42)
Use the information in the table and sequence the six jobs using the critical ratio algorithm.Calculate the average flow times and average lateness.All jobs arrived at time zero and are ready at time zero.


(Essay)
4.8/5
(29)
Table J.11
Work center Q45 has four jobs that just arrived (the start of Day 1)to be processed,as shown in the following table.Assume the shop works eight hours per day.
-Using the information in Table J.11 and the shortest processing time (SPT)rule,what should be the sequence of jobs processed at Q45?

(Multiple Choice)
4.9/5
(42)
Which of the following statements on an operations schedule is BEST?
(Multiple Choice)
4.9/5
(39)
Table J.9
There are three jobs available for processing at Workstation 1.They just arrived at Workstation 1,at the end of Day 0.
-Using the information in Table J.9 and the critical ratio rule,what should be the sequence of jobs processed at Workstation 1?

(Multiple Choice)
4.7/5
(35)
Use the information in the table and sequence the six jobs using SPT and EDD.Calculate the average flow times and average lateness.All jobs arrived at time zero and are ready at time zero.


(Essay)
4.8/5
(30)
Table J.1
The framing department has six jobs waiting to be processed.It is now time zero.Times are expressed in terms of days.
-Using the information in Table J.1 and the EDD rule,what is the average early time?

(Multiple Choice)
4.8/5
(38)
Table J.18
-Use the information in Table J.18 and sequence the jobs using the EDD rule.What is the average flow time?

(Multiple Choice)
5.0/5
(37)