Multiple Choice
In evaluating time-cost tradeoffs, we start by crashing the activity on the critical path that:
A) has the lowest crash cost per unit time.
B) has the lowest total crash cost.
C) can be reduced the most.
D) is the longest.
E) none of the above.
Correct Answer:

Verified
Correct Answer:
Verified