The next three questions relate to the following scenario: Erica is planning a large surprise party for her best friend. She has developed the plan below which includes estimates of the time in hours) and cost necessary to perform each of the activities required.
-To reduce the time for Activity F, Prepare Food, Erica can purchase some of the food from a caterer rather than cook it herself. As shown in the table above, this can reduce the time for Activity F by one or two hours, depending on how much catered food she purchases. What is the crash cost per hour for this activity?
A) $225
B) $475
C) $250
D) $125
E) $83.33
F) None of these, the answer is: ____________________
Correct Answer:

Verified
Correct Answer:
Verified
Q1: Which of the following characteristics would make
Q2: In evaluating time-cost tradeoffs, we start by
Q3: What is the critical chain in the
Q5: Ganesh has been asked to create a
Q6: Using the following figures, what is the
Q7: The next three questions relate to
Q8: When is crashing beneficial to a project?
Q9: Which of the following is most associated
Q10: The next three questions are related to
Q11: The next three questions relate to