Ganesh has been asked to create a project team for a major web development effort. He and the project sponsor have discussed team size and they are debating two options:
-Perform the project in 12 months with a team of 15 people
-Crash the project and complete it in 6 months with a team of 34 people
Which of the following will be true about the contrast between these two options?
A) Option II is likely to require more coordination than Option I.
B) Option I is likely to be more expensive than Option II.
C) Option II will require more than five times as many communication channels as Option I.
D) a and c only.
E) b and c only.
Correct Answer:

Verified
Correct Answer:
Verified
Q1: Which of the following characteristics would make
Q2: In evaluating time-cost tradeoffs, we start by
Q3: What is the critical chain in the
Q4: The next three questions relate to
Q6: Using the following figures, what is the
Q7: The next three questions relate to
Q8: When is crashing beneficial to a project?
Q9: Which of the following is most associated
Q10: The next three questions are related to
Q11: The next three questions relate to