Using the following figures, what is the incremental crash cost for this project activity?
Normal time = 6 months, Crash time = 4 months
Normal cost = $27,000, Crash cost = $35,000
A) $16,000 per month
B) $8,000 per month
C) $4,000 per month
D) $6,000 per month
E) None of the above