Solved

What Is the Difference Between the Critical Path and the Critical

Question 18

Multiple Choice

What is the difference between the critical path and the critical chain?


A) The critical path considers resource availability and the critical chain does not
B) The critical chain considers resource availability and the critical path does not
C) There is no difference - they are exactly the same
D) It is possible to crash activities on the critical path, but activities on the critical chain have already been reduced to their shortest feasible durations.
E) None of the above

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions