Exam 13: Project Evaluation and Control

arrow
  • Select Tags
search iconSearch Question
  • Select Tags

Gap analysis refers to any measurement process that first determines the goals and then the degree to which the actual performance lives up to those goals.

(True/False)
4.9/5
(36)

In earned value management analysis,the cumulative amount of the budget becomes the:

(Multiple Choice)
4.7/5
(38)

Of the three classic metrics of project performance,project S-curve analysis and Gantt charts both consider ________.

(Essay)
4.8/5
(40)

Use the earned value table for Project Terrace to calculate their estimated cost to completion (all dollar amounts are in hundreds). Use the earned value table for Project Terrace to calculate their estimated cost to completion (all dollar amounts are in hundreds).

(Multiple Choice)
4.9/5
(35)

Earned value management allows a project manager to monitor the project's ________,________,and ________.

(Essay)
5.0/5
(32)

What is earned value management and how can it be used to monitor project status?

(Essay)
4.9/5
(39)

A(n)________ identifies the stage of completion each task has attained by a specified date within the project.

(Essay)
4.8/5
(36)

If significant deviations from the project plan are detected,corrective action is taken and then:

(Multiple Choice)
4.9/5
(41)

One of these things is NOT like the others (that happen to directly predict project success).The one that's different is:

(Multiple Choice)
4.8/5
(38)

A project manager that uses milestones as a project control device is using a:

(Multiple Choice)
4.9/5
(44)

Earned value directly links all three primary project success metrics (cost,schedule,and customer satisfaction).

(True/False)
4.9/5
(43)

Use the earned value table for Project Terrace to calculate their estimated time to completion (all dollar amounts are in hundreds). Use the earned value table for Project Terrace to calculate their estimated time to completion (all dollar amounts are in hundreds).

(Multiple Choice)
4.9/5
(46)

The earned value divided by the actual,cumulative cost of the work to date is the:

(Multiple Choice)
4.8/5
(34)

Use the earned value table for Project Terrace to determine the earned value (all dollar amounts are in hundreds). Use the earned value table for Project Terrace to determine the earned value (all dollar amounts are in hundreds).

(Multiple Choice)
4.7/5
(38)

Earned value management is also known as:

(Multiple Choice)
4.9/5
(35)

Use the data to calculate the schedule performance index for the project for the end of week 20.All amounts are in thousands of dollars. Use the data to calculate the schedule performance index for the project for the end of week 20.All amounts are in thousands of dollars.

(Multiple Choice)
4.9/5
(40)

The budget variance is calculated as:

(Multiple Choice)
4.7/5
(46)