Exam 13: Project Evaluation and Control
Exam 1: Introduction: Why Project Management105 Questions
Exam 2: The Organizational Context: Strategy, structure, and Culture106 Questions
Exam 3: Project Selection and Portfolio Management116 Questions
Exam 4: Leadership and the Project Manager130 Questions
Exam 5: Scope Management116 Questions
Exam 6: Project Team Building, conflict, and Negotiation123 Questions
Exam 7: Risk Management114 Questions
Exam 8: Cost Estimation and Budgeting114 Questions
Exam 9: Project Scheduling: Networks, duration Estimation, and Critical Path118 Questions
Exam 10: Project Scheduling: Lagging, crashing, and Activity Networks110 Questions
Exam 11: Critical Chain Project Scheduling117 Questions
Exam 12: Resource Management93 Questions
Exam 13: Project Evaluation and Control117 Questions
Exam 14: Project Closeout and Termination120 Questions
Select questions type
Use the data to calculate the schedule performance index for the project for the end of week 10.All amounts are in thousands of dollars. 

(Multiple Choice)
4.9/5
(30)
In earned value management,schedule variance is defined as:
(Multiple Choice)
4.8/5
(45)
An excellent way to coordinate schedules with vendors and suppliers is through the use of:
(Multiple Choice)
4.8/5
(36)
Use the earned value table to determine the estimated cost to completion (to the nearest hundred dollars)given the indicated state of the project. 

(Multiple Choice)
4.8/5
(32)
Sketch the project control cycle and discuss the activities that take place in each step.
(Essay)
4.9/5
(30)
What is the significance of the 0/100 rule and the 50/50 rule and why would each be used?
(Essay)
4.9/5
(42)
An unmotivated team is a key success inhibitor in every project stage with the exception of the:
(Multiple Choice)
4.9/5
(36)
Use the S-curve where the solid line is actual cost and the dashed line is budgeted cost to choose the best statement. 

(Multiple Choice)
4.9/5
(32)
Measurement mechanisms should include a clear definition of:
(Multiple Choice)
4.8/5
(38)
One strength of S-curve analysis is that it provides real-time tracking information.
(True/False)
4.8/5
(42)
Take the factors considered by earned value analysis and subtract those considered by project S-curves.The factor(s)you have remaining are:
(Multiple Choice)
4.9/5
(41)
Since a project may get ahead of or fall behind schedule,a calendar date cannot be a milestone.
(True/False)
4.9/5
(27)
Inspired by his trip to Greece,the gentleman farmer decided he needed a Mykonos-style windmill pumping a pond for his sheep and orchard.His earned value table for the project appears below.At the end of June,what was the estimated time to completion and the estimated cumulative cost to completion?


(Essay)
4.8/5
(36)
What is a tracking Gantt chart and what are the benefits and drawbacks of its use?
(Essay)
4.9/5
(42)
Use the earned value table (all amounts indicated are dollars)to determine the earned value to the nearest hundred dollars given the indicated state of the project. 

(Multiple Choice)
4.7/5
(34)
Showing 61 - 80 of 117
Filters
- Essay(0)
- Multiple Choice(0)
- Short Answer(0)
- True False(0)
- Matching(0)