Exam 7: Managing Project Resources
Exam 1: Lntroduction to Project Management105 Questions
Exam 2: The Project Management Life Cycle119 Questions
Exam 3: Managing Project Teams139 Questions
Exam 4: Managing Project Communication101 Questions
Exam 5: Managing Project Scope118 Questions
Exam 6: Managing Project Scheduling114 Questions
Exam 7: Managing Project Resources120 Questions
Exam 8: Managing Project Quality127 Questions
Exam 9: Managing Project Risk111 Questions
Exam 10: Managing Project Procurement121 Questions
Exam 11: Managing Project Execution53 Questions
Exam 12: Managing Project Control and Closure110 Questions
Exam 13: Understanding Task Dependencies, Resource Allocation, and Progress Tracking57 Questions
Select questions type
In terms of project time management, resource allocation plays a large role in determining ________
.
(Short Answer)
4.8/5
(36)
Inputs into the activity resource estimating process include:
(Multiple Choice)
4.7/5
(39)
The resources used to complete tasks may also influence the ________ of project deliverables.
(Short Answer)
4.8/5
(33)
________ is an estimating technique in which complex activities are further decomposed to a point where more accurate estimates can be made.
(Multiple Choice)
4.9/5
(36)
The sequence of activities cannot be determined without considering the resources.
(True/False)
4.8/5
(29)
The selection of personnel may be influenced by the availability, costs, and ________ of the resource pool the project manager has access to.
(Short Answer)
4.9/5
(36)
The critical path is the shortest path through a network diagram and shows the shortest time in which a project can be completed.
(True/False)
4.9/5
(35)
The longest path through a network diagram, considering both task dependencies and resource dependencies is called:
(Multiple Choice)
4.7/5
(35)
________ is a technique used to establish contingency reserves during a project to guard against potential risks.
(Multiple Choice)
4.8/5
(32)
In terms of project time management, resource allocation does not affect activity duration.
(True/False)
4.9/5
(41)
________ is performing activities in parallel that would normally be performed in sequence to shorten the duration of a project.
(Short Answer)
4.9/5
(35)
The ________ is a very detailed listing of the resource requirements for the individual activities.
(Multiple Choice)
4.7/5
(32)
The process used to determine the magnitude and criticality of schedule variations is called:
(Multiple Choice)
4.9/5
(41)
List and describe the resource estimation techniques presented in the PMBOK. Also, describe how benchmarking, mind mapping, and brainstorming are used in activity resource estimation. Give examples for each technique.
(Essay)