The critical path in a network diagram illustrates the:

(Multiple Choice)
4.8/5
(34)

The estimation based on the experience of one or more experts on the particular activity or project is called:

(Multiple Choice)
4.9/5
(36)

________ is the process of estimating the duration of the project activities using both project scope and resource information.

(Multiple Choice)
4.8/5
(32)

The critical path is the ________ through a network diagram.

(Short Answer)
4.9/5
(37)

The shortest time in which a project can be completed is shown by the:

(Multiple Choice)
4.8/5
(38)

Capital resources are the tools and ________ used to produce other goods and services.

(Short Answer)
4.9/5
(38)

A(n) ________ is a hierarchical, graphical representation of all needed resources ordered by type or category.

(Multiple Choice)
4.8/5
(27)

Resource allocation:

(Multiple Choice)
4.9/5
(39)

If resources were unlimited, the critical path and the critical chain were ________ .

(Short Answer)
4.9/5
(34)

In critical chain scheduling, a project buffer is used to protect the final due date of a project.

(True/False)
4.8/5
(31)

________ is a process used to determine the magnitude and criticality of schedule variations.

(Short Answer)
4.8/5
(39)

________ are dates that are imposed to meet some form of development deadline.

(Short Answer)
5.0/5
(43)

Human resources include:

(Multiple Choice)
4.8/5
(34)

A Monte Carlo simulation is used for evaluating alternative strategies by observing how changes to selected factors affect other factors and outcomes.

(True/False)
4.9/5
(33)

The elapsed time between start and finish of an activity is referred to as:

(Multiple Choice)
4.9/5
(40)

The combination of resource needs and resource availability helps to determine the time needed to complete the individual activities as well as the entire project.

(True/False)
4.9/5
(29)

For almost any activity, there is a tradeoff between the time needed, the resources invested, and the desired quality of the final deliverable.

(True/False)
4.9/5
(42)

The estimation of activities' durations by averaging optimistic, pessimistic, and most likely estimates is called:

(Multiple Choice)
4.7/5
(45)

All of the following are tools and techniques to estimate resources EXCEPT:

(Multiple Choice)
4.9/5
(38)

The practice of dedicating extra resources to a particular activity in an attempt to finish the activity sooner than the scheduled completion date is called:

(Multiple Choice)
4.9/5
(44)