Exam 14: Operations Scheduling and Sequencing
Exam 1: Operations Management and Value Chains48 Questions
Exam 2: Measuring Performance in Operations and Value Chains35 Questions
Exam 3: Operations Strategy38 Questions
Exam 4: Technology and Operations Management25 Questions
Exam 5: Goods and Service Design40 Questions
Exam 6: Supply Chain Design32 Questions
Exam 7: Process Selection, Design, and Analysis30 Questions
Exam 8: Facility and Work Design31 Questions
Exam 9: Forecasting and Demand Planning35 Questions
Exam 10: Capacity Management34 Questions
Exam 11: Managing Inventories in Supply Chains36 Questions
Exam 12: Supply Chain Management and Logistics25 Questions
Exam 13: Resource Management25 Questions
Exam 14: Operations Scheduling and Sequencing23 Questions
Exam 15: Quality Management38 Questions
Exam 16: Quality Control and SPC25 Questions
Exam 17: Lean Operating Systems26 Questions
Exam 18: Project Management26 Questions
Select questions type
In the context of sequencing, the _____ minimizes the average lateness of a set of jobs.
Free
(Multiple Choice)
5.0/5
(38)
Correct Answer:
A
In the context of operations management,__________refers to the assignment of start and completion times to particular jobs, people, or equipment.
Free
(Multiple Choice)
4.7/5
(45)
Correct Answer:
A
Two examples of process-focused performance measures for sequencing rules are tardiness and lateness.
Free
(True/False)
4.7/5
(41)
Correct Answer:
False
In the context of operations management, triage nurses deciding on the order in which emergency patients are to be treated is an example of _____.
(Multiple Choice)
4.8/5
(39)
There are five jobs in a factory. All these jobs have to go through two workstations for processing. Each job is processed on Workstation #1 and then on Workstation #2. The processing time for each job on each workstation is given below.
Job Time on Workstation \# 1(minutes) Time on Workstation \# 2 (minutes) A 50 50 B 20 8 C 25 50 D 30 12 E 11 22 F 11 19
Using Johnson's sequencing rule, it can be concluded that the makespan of the sequence is:
(Multiple Choice)
4.8/5
(27)
In the context of sequencing, the shortest processing time (SPT) rule tends to:
(Multiple Choice)
4.8/5
(39)
In the context of sequencing,__________is the difference between the completion time and the due date of a job.
(Multiple Choice)
4.8/5
(43)
Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table.
Job Processing Time (days) Due Date A 5 11 B 6 16 C 3 19 D 4 10 E 2 9
Using the earliest due date (EDD) rule, the average lateness for the five jobs is:
(Multiple Choice)
4.8/5
(36)
Five jobs are ready for processing at time zero through a workstation. The details regarding the processing time and the due date of completion is provided in the following table.
Job Processing Time (days) Due Date 6 10 5 17 2 13 3 9 E 4 15
Using the earliest due date (EDD) rule, the average tardiness of the five jobs is:
(Multiple Choice)
4.8/5
(34)
Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table.
Job Processing Time (days) Due Date A 6 18 B 3 14 C 4 9 D 5 19 E 2 11
Using the earliest due date (EDD) rule, the average flow time for the five jobs is _____.
(Multiple Choice)
4.8/5
(30)
An electronic gadgets store requires the following minimum number of employees, each of whom is required to have two consecutive days off.
Day: Mon. Tue. Wed. Thur. Fri. Sat. Sun. Minimum employees required: 9 2 8 6 9 1 3
If there are no day offs provided on Thursday and Friday, the number of employees required to work on Thursday as per the final employee schedule is _____.
(Multiple Choice)
4.9/5
(36)
In the context of sequencing,__________is the amount of time by which the completion time exceeds the due date of a job.
(Multiple Choice)
4.8/5
(30)
In the context of sequencing, the earliest due date (EDD) rule:
(Multiple Choice)
4.9/5
(35)
A new surgical facility called Cut & Sew has opened in the United States. The branches of the facility are spread throughout the country. These are job shops that handle a variety of outpatient surgical procedures. The process of the facility is set up in a way that one doctor will cut and another will sew. The data regarding the patients and the estimated time for cutting and sewing for each patient are given in the following table:
Patient Cut Time (hours) Sew Time (hours) 2.3 2.8 2.5 3.0 2.0 1.5 0.6 1.0 3.6 2.6
Using Johnson's sequencing rule, the final sequence of the patients is _____.
(Multiple Choice)
4.9/5
(39)
The Clarke-Wright Heuristic Method is used to solve the common scheduling problem in logistics that involves determining routes from a central depot or warehouse to many customers.
(True/False)
4.8/5
(30)
Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table.
Job Processing Time (days) Due Date 8 12 4 9 3 6 7 7 5 20
Using the shortest processing time (SPT) rule, it can be concluded that the average flow time for these five jobs is _____.
(Multiple Choice)
4.8/5
(36)
Different industries use different software packages for scheduling because every industry has different problem structures.
(True/False)