Exam 17: Statistical Applications in Quality Management
Exam 1: Introduction145 Questions
Exam 2: Organizing and Visualizing Data210 Questions
Exam 3: Numerical Descriptive Measures153 Questions
Exam 4: Basic Probability171 Questions
Exam 5: Discrete Probability Distributions218 Questions
Exam 6: The Normal Distribution and Other Continuous Distributions191 Questions
Exam 7: Sampling and Sampling Distributions197 Questions
Exam 8: Confidence Interval Estimation196 Questions
Exam 9: Fundamentals of Hypothesis Testing: One-Sample Tests165 Questions
Exam 10: Two-Sample Tests210 Questions
Exam 11: Analysis of Variance213 Questions
Exam 12: Chi-Square Tests and Nonparametric Tests201 Questions
Exam 13: Simple Linear Regression213 Questions
Exam 14: Introduction to Multiple Regression355 Questions
Exam 15: Multiple Regression Model Building96 Questions
Exam 16: Time-Series Forecasting168 Questions
Exam 17: Statistical Applications in Quality Management133 Questions
Exam 18: A Roadmap for Analyzing Data54 Questions
Exam 19: Questions that Involve Online Topics321 Questions
Select questions type
TABLE 17-1
A local newspaper has 10 delivery boys who each deliver the morning paper to 50 customers every day. The owner decides to record the number of papers delivered on time for a 10-day period for one of the delivery boys and construct a p chart to see whether the percentage is too erratic.
-Referring to Table 17-1, what is the numerical value of the lower control limit for the p chart?

(Multiple Choice)
4.8/5
(31)
TABLE 17-9
The manufacturer of canned food constructed control charts and analyzed several quality characteristics. One characteristic of interest is the weight of the filled cans. The lower specification limit for weight is 2.95 pounds. The table below provides the range and mean of the weights of five cans tested every fifteen minutes during a day's production.
-Referring to Table 17-9, an R chart is to be constructed for the weight. One way to create the lower control limit involves multiplying the mean of the sample ranges by D₃. For this data set, the value of D₃ is ________.

(Short Answer)
4.9/5
(20)
TABLE 17-8
Recently, a university switched to a new type of computer-based registration. The registrar is concerned with the amount of time students are spending on the computer registering under the new system. She decides to randomly select 8 students on each of the 12 days of the registration and determine the time each spends on the computer registering. The range, mean, and standard deviation of the times required to register are in the table that follows.
-Referring to Table 17-8, an
chart is to be used for the time required to register. One way to obtain the control limits is to take the grand mean and add and subtract the product of A₂ times the mean of the sample ranges. For this data set, the value of A₂ is ________.


(Short Answer)
4.9/5
(33)
Larger Cpk indicates larger capability of meeting the requirements.
(True/False)
4.7/5
(25)
TABLE 17-3
A quality control analyst for a light bulb manufacturer is concerned that the time it takes to produce a batch of light bulbs is too erratic. Accordingly, the analyst randomly surveys 10 production periods each day for 14 days and records the sample mean and range for each day.
-Referring to Table 17-3, suppose the sample mean and range data were based on 11 observations per day instead of 10. How would this change affect the lower and upper control limits of the R chart?

(Multiple Choice)
4.8/5
(32)
An in-control process must be achieved before being able to estimate process capability.
(True/False)
4.8/5
(37)
TABLE 17-9
The manufacturer of canned food constructed control charts and analyzed several quality characteristics. One characteristic of interest is the weight of the filled cans. The lower specification limit for weight is 2.95 pounds. The table below provides the range and mean of the weights of five cans tested every fifteen minutes during a day's production.
-Referring to Table 17-9, based on
the chart, it appears that the process is in control.


(True/False)
4.8/5
(32)
Referring to Table 17-7, what percentage of the chips will fall below the upper specification limit?
(Short Answer)
4.9/5
(44)
TABLE 17-6
The maker of a packaged candy wants to evaluate the quality of her production process. On each of 16 consecutive days, she samples 600 bags of candy and determines the number in each day's sample that she considers to be of poor quality. The data that she developed follow.
-Referring to Table 17-6, a p control chart is to be constructed for these data. The lower control limit is ________, while the upper control limit is ________.

(Short Answer)
4.8/5
(34)
TABLE 17-10
Below is the number of defective items from a production line over twenty consecutive morning shifts.
-Referring to Table 17-10, a c chart is to be constructed for the number of defective items. The center line of this c chart is located at ________.

(Short Answer)
4.7/5
(34)
The smaller the capability index, the more capable a process is of meeting customer requirements.
(True/False)
4.8/5
(32)
TABLE 17-9
The manufacturer of canned food constructed control charts and analyzed several quality characteristics. One characteristic of interest is the weight of the filled cans. The lower specification limit for weight is 2.95 pounds. The table below provides the range and mean of the weights of five cans tested every fifteen minutes during a day's production.
-Referring to Table 17-9, an
chart is to be used for the weight. The center line of this chart is located at ________.


(Short Answer)
4.9/5
(29)
________ causes of variation are correctable without modifying the system.
(Short Answer)
4.9/5
(31)
TABLE 17-7
A supplier of silicone sheets for producers of computer chips wants to evaluate her manufacturing process. She takes samples of size 5 from each day's output and counts the number of blemishes on each silicone sheet. The results from 20 days of such evaluations are presented below.
-Referring to Table 17-7, construct an R chart for the number of blemishes.

(Essay)
4.9/5
(34)
TABLE 17-9
The manufacturer of canned food constructed control charts and analyzed several quality characteristics. One characteristic of interest is the weight of the filled cans. The lower specification limit for weight is 2.95 pounds. The table below provides the range and mean of the weights of five cans tested every fifteen minutes during a day's production.
-Referring to Table 17-9, an
chart is to be used for the weight. The lower control limit for this data set is ________, while the upper control limit is ________.


(Short Answer)
4.8/5
(34)
Referring to Table 17-7, an
chart is to be used for the number of blemishes. The lower control limit for this data set is ________, while the upper control limit is ________.

(Short Answer)
4.8/5
(36)
TABLE 17-4
A factory supervisor is concerned that the time it takes workers to complete an important production task (measured in seconds) is too erratic and adversely affects expected profits. The supervisor proceeds by randomly sampling 5 individuals per hour for a period of 10 hours. The sample mean and range for each hour are listed below.
She also decides that lower and upper specification limit for the critical-to-quality variable should be 10 and 30 seconds, respectively.
-Referring to Table 17-4, suppose the supervisor constructs an R chart to see if the variability in collection times is in-control. What are the lower and upper control limits for this R chart?

(Multiple Choice)
4.8/5
(41)
TABLE 17-4
A factory supervisor is concerned that the time it takes workers to complete an important production task (measured in seconds) is too erratic and adversely affects expected profits. The supervisor proceeds by randomly sampling 5 individuals per hour for a period of 10 hours. The sample mean and range for each hour are listed below.
She also decides that lower and upper specification limit for the critical-to-quality variable should be 10 and 30 seconds, respectively.
-Referring to Table 17-4, suppose the sample mean and range data were based on 6 observations per hour instead of 5. How would this change affect the lower and upper control limits of an R chart?

(Multiple Choice)
5.0/5