Exam 7: Managing Risk

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Enhancing a risk is a tactic that seeks to eliminate the uncertainty associated with an opportunity to ensure that it definitely happens.

Free
(True/False)
4.9/5
(36)
Correct Answer:
Verified

False

The risk management tool that is divided into three color-coded zones representing major, moderate, and minor risks is the risk

Free
(Multiple Choice)
4.8/5
(36)
Correct Answer:
Verified

E

Opportunities identified within a project are treated very differently from risks.

Free
(True/False)
4.8/5
(31)
Correct Answer:
Verified

False

Purchasing an accident insurance policy would be an example of responding to a risk by _____________ it.

(Multiple Choice)
4.9/5
(37)

Which of the following is NOT one of the steps in the risk management process?

(Multiple Choice)
4.8/5
(37)

A ____________ (responsible for the work package)involved in risk assessment and mitigation will help focus attention on all aspects of risk management.

(Multiple Choice)
4.8/5
(31)

The implications of an identified change need to be assessed by:

(Multiple Choice)
4.9/5
(33)

Testing a new project on a smaller isolated area prior to installing it for the entire organization is an example of ________ a risk.

(Short Answer)
4.7/5
(35)

Risk events that occur in the early stages of a project will have a greater cost impact than those that occur in later stages.

(True/False)
4.9/5
(36)

A list of questions that address traditional areas of uncertainty on a project is termed a

(Multiple Choice)
4.7/5
(25)

What is the difference between mitigating a risk and a contingency plan? Provide real life examples that illustrate the difference.

(Essay)
4.9/5
(26)

Budget reserves are set up to cover identified risks associated with specific segments of a project while management reserves are set up to cover unidentified risks associated with the total project.

(True/False)
4.7/5
(32)

An unanticipated event that occurs which is beneficial to a project is known as a(n)

(Multiple Choice)
4.7/5
(31)

Fixed-price contracts are an example of transferring risk from an owner to a contractor.

(True/False)
4.9/5
(41)

Identify and briefly describe the four steps in the risk management process.

(Essay)
4.8/5
(41)

The ________ matrix is divided into red, yellow, and green zones representing major, moderate, and minor risks.

(Short Answer)
4.9/5
(29)

This response is used to increase the potential effect of an identified Opportunity.

(Multiple Choice)
4.9/5
(38)

If, during risk response development, you successfully identify how you will respond to a risk, contingency planning is unnecessary.

(True/False)
4.9/5
(28)

Having an environment where identified risks are treated professionally will lead to better control of risks.

(True/False)
5.0/5
(35)

Although most risks are presented as something not desirable, there can also be desirable risks called Opportunities.

(True/False)
4.7/5
(27)
Showing 1 - 20 of 98
close modal

Filters

  • Essay(0)
  • Multiple Choice(0)
  • Short Answer(0)
  • True False(0)
  • Matching(0)