Exam 8: Scheduling Resources and Costs
Exam 1: Modern Project Management98 Questions
Exam 2: Organization Strategy and Project Selection97 Questions
Exam 3: Organization: Structure and Culture101 Questions
Exam 4: Defining the Project99 Questions
Exam 5: Estimating Project Times and Costs101 Questions
Exam 6: Developing a Project Plan105 Questions
Exam 7: Managing Risk98 Questions
Exam 8: Scheduling Resources and Costs102 Questions
Exam 9: Reducing Project Duration106 Questions
Exam 10: Being an Effective Project Manager101 Questions
Exam 11: Managing Project Team106 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations105 Questions
Exam 13: Progress and Performance Measurement and Evaluation101 Questions
Exam 14: Project Closure99 Questions
Exam 15: International Projects107 Questions
Exam 16: An Introduction to Agile Project Management98 Questions
Select questions type
Resource bottlenecks are one of the three more common problems encountered in managing multiproject resource schedules.
Free
(True/False)
4.9/5
(42)
Correct Answer:
True
A(n)________ constraint addresses the sequence in which project activities must occur even after considering resource constraints.
Free
(Short Answer)
4.9/5
(28)
Correct Answer:
technical or logic
Explanation: The start and sequence of activities have been based solely on technical or logical considerations.For example, a project network for framing a house might show three activities in a sequence:
(1)pour foundation, (2)build frame, and (3)cover roof.Resource constraints do not violate technical constraints.
The shortage of computer chips to produce a circuit board is an example of a(n)________ type of resource constraint.
Free
(Short Answer)
4.9/5
(35)
Correct Answer:
materials
Explanation: Material availability and shortages have been blamed for the delay of many projects.When it is known that a lack of availability of materials is important and probable, materials should be included in the project network plan and schedule.
When scheduling activities in a resource-constrained project, typically the activity scheduled first has the __________ amount of slack.
(Short Answer)
4.8/5
(31)
When scheduling activities in a resource-constrained project typically the activity scheduled first has the most amount of slack.
(True/False)
4.9/5
(38)
Tony has realized that two activities in his project cannot be done at the same time because not enough resources are available.Activity 3 is critical and has a duration of 5 days.Activity 4 has 2 days of slack and a duration of 2 days.How will he decide which activity should be scheduled first?
(Multiple Choice)
4.8/5
(30)
Identify and give an example of the three types of resource constraints.
(Essay)
4.8/5
(38)
In a resource-constrained project, the completion date is most likely to change.
(True/False)
5.0/5
(33)
Resources are adequate, but demand varies widely over the life of the project.Delaying noncritical activities to lower peak demand on resources is known as resource
(Multiple Choice)
4.8/5
(34)
A special truck that George needs on his project has been scheduled on another project.This is an example of what type of resource constraint?
(Multiple Choice)
4.8/5
(34)
If three copiers are needed to produce a final report on time and only two are available, the project is facing a(n)________ type of resource constraint.
(Short Answer)
4.8/5
(31)
Since resource leveling or smoothing delays noncritical activities, a common result is an increase in network ___________.
(Short Answer)
4.9/5
(48)
If resources are not adequate to meet peak demands, the resulting reschedule is termed
(Multiple Choice)
4.9/5
(46)
A project budget report is showing our project as spending $35,000 against a budgeted amount of $40,000.Which of the following is true?
(Multiple Choice)
4.9/5
(27)
In scheduling resource-constrained projects, _________ are typically used rather than optimum mathematical solutions.
(Short Answer)
4.8/5
(30)
When there are not enough people, money, and/or equipment available for a project it is known as being
(Multiple Choice)
4.9/5
(37)
This is used to compare the cost accounts between organizational units and deliverables.
(Multiple Choice)
4.9/5
(33)
Project budgets are developed by time-phasing which of the following?
(Multiple Choice)
4.9/5
(37)
In reviewing the status of her project with top management, Shirley was told that there are only two programmers that she can use for her project.Her project is classified as __________ constrained.
(Multiple Choice)
4.9/5
(37)
Resource constraints can be overcome by creative and efficient scheduling.
(True/False)
4.8/5
(25)