Exam 6: Developing a Project Plan
Exam 1: Modern Project Management98 Questions
Exam 2: Organization Strategy and Project Selection97 Questions
Exam 3: Organization: Structure and Culture101 Questions
Exam 4: Defining the Project99 Questions
Exam 5: Estimating Project Times and Costs101 Questions
Exam 6: Developing a Project Plan105 Questions
Exam 7: Managing Risk98 Questions
Exam 8: Scheduling Resources and Costs102 Questions
Exam 9: Reducing Project Duration106 Questions
Exam 10: Being an Effective Project Manager101 Questions
Exam 11: Managing Project Team106 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations105 Questions
Exam 13: Progress and Performance Measurement and Evaluation101 Questions
Exam 14: Project Closure99 Questions
Exam 15: International Projects107 Questions
Exam 16: An Introduction to Agile Project Management98 Questions
Select questions type
When translated into a project network, a work package will become
Free
(Multiple Choice)
4.9/5
(33)
Correct Answer:
B
What is the Concurrent Engineering Approach and why should project managers be aware of it?
Free
(Essay)
4.9/5
(27)
Correct Answer:
The chainlike sequence of finish-to-start relationships is replaced by a series of start-to-start lag relationships as soon as meaningful work can be initiated for the next phase.The resulting overlap of tasks slightly increases risk but results in a much shorter schedule.
The critical path in a project network is the
Free
(Multiple Choice)
4.9/5
(32)
Correct Answer:
B
How does the WBS differ from the project network? How are WBS and project networks linked?
(Essay)
4.9/5
(32)
A _________ activity is one that has more than one activity taking place at the same time.
(Multiple Choice)
4.7/5
(46)
An activity that has more than one dependency arrow flowing into it is termed a(n)
(Multiple Choice)
4.8/5
(32)
A(n)_________ activity has more than one dependency arrow flowing from it.
(Multiple Choice)
4.7/5
(32)
The backward pass through a project network determines slack or how long an activity can be delayed without impacting the completion date of the project.
(True/False)
4.9/5
(30)
Burst activities have more than one activity immediately following them (more than one dependency arrow flowing from them).
(True/False)
4.7/5
(35)
If a network has more than one critical path but noncritical activities have very little slack, the network is considered to have a high level of sensitivity.
(True/False)
4.8/5
(31)
The amount of delay within a task that will not delay the overall project is known as a
(Multiple Choice)
4.9/5
(30)
Which of the following represents an activity on an activity-on-node (AON)project network?
(Multiple Choice)
4.8/5
(35)
A project network provides the basis for ________________________________ .
(Multiple Choice)
4.8/5
(34)
If testing cannot be completed any earlier than four days after the prototype has been built, what type of lag exists?
(Multiple Choice)
4.7/5
(30)
In developing a project network, neither looping nor conditional statements are permitted.
(True/False)
4.8/5
(33)
Activities which can take place at the same time are termed
(Multiple Choice)
4.8/5
(35)
________ activities must be completed immediately before a particular activity.
(Multiple Choice)
4.9/5
(35)
The longest path through a project network is called the _________.
(Short Answer)
4.9/5
(36)
After the total slack for each activity is identified, the project manager can more easily identify the __________________.
(Multiple Choice)
4.9/5
(32)