Exam 13: Progress and Performance Measurement and Evaluation
Exam 1: Modern Project Management98 Questions
Exam 2: Organization Strategy and Project Selection97 Questions
Exam 3: Organization: Structure and Culture101 Questions
Exam 4: Defining the Project99 Questions
Exam 5: Estimating Project Times and Costs101 Questions
Exam 6: Developing a Project Plan105 Questions
Exam 7: Managing Risk98 Questions
Exam 8: Scheduling Resources and Costs102 Questions
Exam 9: Reducing Project Duration106 Questions
Exam 10: Being an Effective Project Manager101 Questions
Exam 11: Managing Project Team106 Questions
Exam 12: Outsourcing: Managing Interorganizational Relations105 Questions
Exam 13: Progress and Performance Measurement and Evaluation101 Questions
Exam 14: Project Closure99 Questions
Exam 15: International Projects107 Questions
Exam 16: An Introduction to Agile Project Management98 Questions
Select questions type
In monitoring project time (schedule)performance, actual performance should be compared to
Free
(Multiple Choice)
4.7/5
(32)
Correct Answer:
C
A CPI index of 0.97 indicates that the project has spent less money than budgeted.
Free
(True/False)
4.8/5
(43)
Correct Answer:
False
The ________ variance is the difference between the earned value and the actual costs for the work completed to date.
Free
(Short Answer)
4.8/5
(28)
Correct Answer:
cost
Explanation: Cost variance is the difference between the earned value and the actual costs for the work completed to date where CV = EV - AC.
In some cases, conditions or scope can change, which, in turn, will require a change in the baseline plan to recognize new information.
(True/False)
4.9/5
(34)
A CPI or SPI value less than one indicates that the project is
(Multiple Choice)
4.9/5
(35)
Conditions or scope can change, which, in turn, will require a change to the __________ plan to recognize the new information.
(Short Answer)
4.8/5
(39)
Baseline project budgets are derived from time-phasing the work ________.
(Short Answer)
4.9/5
(27)
Because of their easy-to-understand visual format, tracking Gantt charts are the most favored, used, and understandable option for reporting project status.
(True/False)
4.9/5
(33)
The ________ variance is the difference between the earned value to date and the baseline schedule.
(Short Answer)
4.9/5
(37)
________ is simply the percent complete times the original budget.
(Short Answer)
4.9/5
(36)
A reason that the duration on a task may differ from an original duration on a Tracking Gantt chart could be
(Multiple Choice)
4.9/5
(42)
Two major reasons for creating a baseline are to monitor and report progress and to estimate cash flow.
(True/False)
4.8/5
(27)
For a more complex project, statistical analysis can be applied to a Control Chart to identify potential causes of schedule deviation.
(True/False)
4.8/5
(34)
Although it is very difficult to measure, measuring ________ performance is as important as measuring schedule and cost performance.
(Short Answer)
4.9/5
(36)
An SPI index of 1.22 indicates that the project is ________ of schedule.
(Short Answer)
4.8/5
(40)
Showing 1 - 20 of 101