Exam 13: Progress and Performance Measurement and Evaluation

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

In monitoring project time (schedule)performance, actual performance should be compared to

Free
(Multiple Choice)
4.7/5
(32)
Correct Answer:
Verified

C

A CPI index of 0.97 indicates that the project has spent less money than budgeted.

Free
(True/False)
4.8/5
(43)
Correct Answer:
Verified

False

The ________ variance is the difference between the earned value and the actual costs for the work completed to date.

Free
(Short Answer)
4.8/5
(28)
Correct Answer:
Verified

cost
Explanation: Cost variance is the difference between the earned value and the actual costs for the work completed to date where CV = EV - AC.

In some cases, conditions or scope can change, which, in turn, will require a change in the baseline plan to recognize new information.

(True/False)
4.9/5
(34)

A CPI or SPI value less than one indicates that the project is

(Multiple Choice)
4.9/5
(35)

Conditions or scope can change, which, in turn, will require a change to the __________ plan to recognize the new information.

(Short Answer)
4.8/5
(39)

The cost variance for a project is calculated by

(Multiple Choice)
4.7/5
(22)

Baseline project budgets are derived from time-phasing the work ________.

(Short Answer)
4.9/5
(27)

Of the following costs, which are NOT included in baseline?

(Multiple Choice)
4.7/5
(30)

Because of their easy-to-understand visual format, tracking Gantt charts are the most favored, used, and understandable option for reporting project status.

(True/False)
4.9/5
(33)

Baseline project budgets are derived from

(Multiple Choice)
4.7/5
(28)

The ________ variance is the difference between the earned value to date and the baseline schedule.

(Short Answer)
4.9/5
(37)

________ is simply the percent complete times the original budget.

(Short Answer)
4.9/5
(36)

A reason that the duration on a task may differ from an original duration on a Tracking Gantt chart could be

(Multiple Choice)
4.9/5
(42)

Two major reasons for creating a baseline are to monitor and report progress and to estimate cash flow.

(True/False)
4.8/5
(27)

A project manager would be glad to see a TCPI of 1.07.

(True/False)
4.8/5
(33)

Causes for Scope Creep can include

(Multiple Choice)
4.9/5
(33)

For a more complex project, statistical analysis can be applied to a Control Chart to identify potential causes of schedule deviation.

(True/False)
4.8/5
(34)

Although it is very difficult to measure, measuring ________ performance is as important as measuring schedule and cost performance.

(Short Answer)
4.9/5
(36)

An SPI index of 1.22 indicates that the project is ________ of schedule.

(Short Answer)
4.8/5
(40)