Exam 16: An Introduction to Agile Project Management

arrow
  • Select Tags
search iconSearch Question
flashcardsStudy Flashcards
  • Select Tags

Identify and describe two limits or concerns associated with agile project management.

Free
(Essay)
4.8/5
(37)
Correct Answer:
Verified

(1)Agile project management doesn't satisfy top management's need for budget, scope and schedule control.
(2)Many of the agile principles, including self-organizing teams and intense collaboration, are incompatible with corporate cultures.
(3)Agile requires active customer involvement.

The more the project scope is unknown, the ___________ of the project will be greater

Free
(Short Answer)
4.9/5
(40)
Correct Answer:
Verified

uncertainty
Explanation: The more that this not known about the project when you begin, the more likely there is for change, putting budget and schedule at risk.

_____________ represents a fundamental shift away from the traditional plan-driven project management approach by adopting a more experimental and adaptive approach to managing projects.

Free
(Multiple Choice)
4.7/5
(38)
Correct Answer:
Verified

A

While agile project management does not consist of one set method, most methods are based on similar principles.Which of the following agile project management principles would be described when team members decide among themselves who should do what and what should be done?

(Multiple Choice)
4.8/5
(39)

The purpose of release planning is to establish the goals and a general WBS for the project.

(True/False)
4.8/5
(37)

When considering the agile project management process, at the end of each iteration

(Multiple Choice)
5.0/5
(36)

The goal of each sprint is to produce fully functional features.

(True/False)
4.8/5
(34)

In Scrum methodology, it is important to make sure roles and titles are clear when developing a team.

(True/False)
4.9/5
(34)

Project ________ varies according to the extent the project scope is known and stable and the technology to be used is known and proven.

(Multiple Choice)
4.8/5
(35)

_______________ is the Agile principle that prescribes the project team learning, reflecting and adapting to change within the Project

(Multiple Choice)
4.9/5
(36)

The ____________ facilitates the Scrum process and resolves impediments at the team and organizational level.

(Short Answer)
4.9/5
(35)

A new holistic approach in new commercial product development efforts where the cross-functional team collaborating to develop a new product is compared to rugby, where the whole team tries to go the distance as a unit, is known as _________.

(Short Answer)
4.7/5
(38)

Using Scrum methodology, specific features are created according to four distinct phases during each sprint.The third phase is to ________ the feature so that it is functional.

(Short Answer)
4.8/5
(36)

Each new iteration replaces the work of the previous iterations and adds new capabilities to the evolving to produce a next expanded version of the product.

(True/False)
4.9/5
(32)

When the project scope and/or technology are not fully known, things become much less predictable.

(True/False)
4.9/5
(36)

A new holistic approach in new commercial product development efforts where the cross-functional team collaborating to develop a new product is compared to rugby, where the whole team tries to go the distance as a unit is known as

(Multiple Choice)
4.8/5
(40)

Agile methods appear to work best on __________ projects that require only five to nine dedicated team members to complete the work.

(Short Answer)
4.8/5
(39)

The product owner has the option to change features and priorities at the end of each sprint if desired.

(True/False)
4.9/5
(45)

Using traditional approaches to project management, once the project scope has been firmly established, every detail of the project is defined through the ________.

(Multiple Choice)
4.8/5
(25)

While agile project management does not consist of one set method, most methods are based on similar principles.Which of the following agile project management principles would be described when teams reflect, learn, and adapt to change, and when project work updates the plan?

(Multiple Choice)
4.8/5
(37)
Showing 1 - 20 of 98