Lot-for-lot ordering in MRP minimizes holding costs for parts that are carried over to other periods.

Free
(True/False)
4.8/5
(33)
Correct Answer:
Verified

True

MRP is used within MRP II systems.

Free
(True/False)
4.8/5
(26)
Correct Answer:
Verified

True

A computer-based information system designed to handle ordering and scheduling of dependent-demand items is used for:

Free
(Multiple Choice)
4.8/5
(31)
Correct Answer:
Verified

D

Load reports show capacity requirements for departments or work centers which may be more or less than the capacity available in that work center.

(True/False)
4.9/5
(34)

The identification of parent items that have generated a given set of material requirements for an item is called:

(Multiple Choice)
4.9/5
(42)

The gross requirements at one level of an MRP plan determine the gross requirements at the next lower level continuing on down to the lowest levels shown on the bill of materials.

(True/False)
4.8/5
(35)

A regenerative MRP system is one that is updated continuously, every time there is a schedule change.

(True/False)
4.9/5
(39)

The term pegging refers to identifying the parent items that have generated a given set of material requirements for a part or subassembly.

(True/False)
4.8/5
(43)

The gross requirements value for any given component is equal to the net requirements of that component's immediate parent multiplied by the quantity per parent.

(True/False)
4.9/5
(39)

An MRP system whose records are updated continuously is referred to as a(n):

(Multiple Choice)
4.9/5
(32)

The bill of materials contains information on lead times and current inventory position on every component required to produce the end item.

(True/False)
4.8/5
(38)

MRP II did not replace the basic MRP.

(True/False)
4.7/5
(32)

The inventory records contain information on the status of each item by time period.

(True/False)
4.7/5
(37)

ERP implementation probably will not require:

(Multiple Choice)
5.0/5
(40)

MRP II is simply an improved version of MRP that processes more quickly and can plan for a larger number of end items.

(True/False)
4.8/5
(29)

Under lot-for-lot, order sizes for component parts are essentially determined directly from which one of the following?

(Multiple Choice)
4.9/5
(36)

Backflushing takes place:

(Multiple Choice)
4.7/5
(34)

Project management approaches can help in a conversion to an ERP system.

(True/False)
4.7/5
(31)

An effort to expand the scope of material planning by involving other functional areas in the planning process has been:

(Multiple Choice)
4.7/5
(40)

Which of these products would be most likely to have dependent demand?

(Multiple Choice)
4.8/5
(44)